Section of the table from the Solispec engine (median zone — Cherkasy)

REC

Ground frame for 40 REC Alpha Pro MG REC610AA Pro MG (HJT, bifacial) panels (4×10)

4 rows of 10 panels, 24.40 kW. The Solispec engine chose the profiles, the frame pitch and the footings for three snow and wind zones: Kherson has the lowest load of the regional centres, Cherkasy the median, Chernihiv the highest.

Power
24.40kW
Steel
1,298.9kg
Posts
21
Bolts
316
Materials
176,581₴
Yield
27,786kWh/year

Figures for the median zone (Cherkasy); all three zones are in the table below.

Ground frame designer

Open this frame in the builder

The builder opens with the REC Alpha Pro MG REC610AA Pro MG (HJT, bifacial) panel and the 4 × 10 layout; site — Cherkasy. Change the site, the tilt or the profiles and the checks and estimate are recalculated.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Three snow and wind zones

The same table designed for three regional centres: with the lowest, the median and the highest combined snow and wind load under DBN V.1.2-2:2006. For another site, open the frame in the builder.

ParameterLow loadKherson · S₀ 760 · W₀ 480Median loadCherkasy · S₀ 1,520 · W₀ 420High loadChernihiv · S₀ 1,720 · W₀ 410
PostsTube 80×80×3Tube 80×80×3Tube 80×80×3
RaftersTube 60×60×2C-channel 100×50×2.5C-channel 100×50×2.5
Purlins and bracesC-channel 41×41×2.5C-channel 60×40×2C-channel 41×41×2.5
Frames10 frames, pitch up to 1,440 mm7 frames, pitch up to 2,120 mm10 frames, pitch up to 1,440 mm
Posts302130
Footings (bored concrete)30 pcs, Ø450 mm, depth 1,500 mm21 pcs, Ø500 mm, depth 1,700 mm30 pcs, Ø400 mm, depth 1,500 mm
Concrete7.87 m³7.71 m³6.22 m³
Tilt30°30°30°
Panel bottom / post top600 / 4,149 mm600 / 4,115 mm600 / 4,131 mm
Panel field size13,370 × 6,288 mm13,370 × 6,308 mm13,370 × 6,298 mm
Row spacing between tables (no shade on 21 December)19,650 mm at noon · 22,090 mm ±2 h21,780 mm at noon · 25,150 mm ±2 h23,870 mm at noon · 28,370 mm ±2 h
Steel1,657.1 kg1,298.9 kg1,677.2 kg
BoltsM10 — 294, M8 — 88M10 — 228, M8 — 88M10 — 294, M8 — 88
Panel clampsend 16, middle 72end 16, middle 72end 16, middle 72
Materials182,345 UAH176,581 UAH197,345 UAH
With installation and delivery244,827 UAH238,446 UAH258,867 UAH
Per 1 kW10,034 UAH/kW9,772 UAH/kW10,609 UAH/kW
Yield1,266 kWh/kW · 30,901 kWh/year1,139 kWh/kW · 27,786 kWh/year1,043 kWh/kW · 25,452 kWh/year
Strength σ/fy61%97%86%
Deflection / (L/200)44%81%61%
Rafter strength95%98%71%
Post utilisation20%39%28%
Post utilisation П36%12%9%
Utilisation97%97%96%
Depth vs frost depthokokok
Bolt utilisation27%66%48%
Plate section11%11%8%
Not includedengineer to checkengineer to checkengineer to check
Checks overallwith a cautionwith a cautionwith a caution

Checks and cautions

Member utilisation as the engine computes it. Cautions are checks that pass, but with a small margin.

  • Rafter profileThe rafter is used above 80 %, or the frame's posts stand far apart: the structure passes, but the margin is small.Kherson: Rafter · Tube 60×60×2 · 3 posts, spans between posts 2 840 mm, cantilever 1 160 mm — continuous beam on 3 supports → strength 95%.Cherkasy: Rafter · C-channel 100×50×2.5 · 3 posts, spans between posts 2 840 mm, cantilever 1 160 mm — continuous beam on 3 supports → strength 98%.
  • Embedment, mmThe footing resists wind uplift at above 80 % utilisation, or it is shallower than the frost depth. The soil resistance in the calculation is an estimate — check the soil on site.Kherson: Foundation Ø450 × 1 500: 0.239 m³ of concrete per post. Wind uplift on the front post ≈ 20.5 kN (with γ=1.5) vs ≈ 21.1 kN (concrete weight + soil friction, estimate) → 97%.Cherkasy: Foundation Ø500 × 1 700: 0.334 m³ of concrete per post. Wind uplift on the front post ≈ 26.4 kN (with γ=1.5) vs ≈ 27.2 kN (concrete weight + soil friction, estimate) → 97%.Chernihiv: Foundation Ø400 × 1 500: 0.188 m³ of concrete per post. Wind uplift on the front post ≈ 17.5 kN (with γ=1.5) vs ≈ 18.2 kN (concrete weight + soil friction, estimate) → 96%.
  • Stock length, mmKherson: Rafter 8 000 mm is longer than the 6 000 mm stock length — 2 pieces: Кр1а 3 300, Кр1б 4 700 mm. Splice — plate Н1 L 300 mm of the same profile, back to back, 2+2 bolts M10 cl. 8.8, at 3 300 mm from the lower end of the rafter, where the moment is small. Bolt: 6.09 kN vs 22.27 kN (27%), plate 11%. Rafter splice — engineer to check: the plate's eccentricity, the C-channel's torsion and the axial force are not included.Cherkasy: Rafter 8 000 mm is longer than the 6 000 mm stock length — 2 pieces: Кр1а 3 300, Кр1б 4 700 mm. Splice — plate Н1 L 300 mm of the same profile, back to back, 2+2 bolts M10 cl. 8.8, at 3 300 mm from the lower end of the rafter, where the moment is small. Bolt: 11.84 kN vs 18.00 kN (66%), plate 11%. Rafter splice — engineer to check: the plate's eccentricity, the C-channel's torsion and the axial force are not included.Chernihiv: Rafter 8 000 mm is longer than the 6 000 mm stock length — 2 pieces: Кр1а 3 300, Кр1б 4 700 mm. Splice — plate Н1 L 300 mm of the same profile, back to back, 2+2 bolts M10 cl. 8.8, at 3 300 mm from the lower end of the rafter, where the moment is small. Bolt: 8.59 kN vs 18.00 kN (48%), plate 8%. Rafter splice — engineer to check: the plate's eccentricity, the C-channel's torsion and the axial force are not included.
  • Max. frame pitch, mmThe purlins between the frames are used above 80 % (strength or deflection): the structure passes, but the margin is small. A shorter frame pitch or a deeper purlin gives more margin.Cherkasy: Frame spacing 2 120 mm, 7 frames. Purlin C-channel 60×40×2: strength 97%, deflection 81% of L/200 (snow on panel 977 Pa).Chernihiv: Frame spacing 1 440 mm, 10 frames. Purlin C-channel 41×41×2.5: strength 86%, deflection 61% of L/200 (snow on panel 1 106 Pa).

Bill of materials

The parts of one table for the median zone (Cherkasy): mark, name, profile, cut length, quantity.

MarkPartProfileLength, mmQuantity
П1Front postTube 80×80×33,0007
П2Rear postTube 80×80×35,8407
П3Middle postTube 80×80×34,4207
Кр1аRafter (inclined beam)C-channel 100×50×2.53,3007
Кр1бRafter (inclined beam)C-channel 100×50×2.54,7007
Н1Rafter splice plateC-channel 100×50×2.53007
Пк1Frame strutC-channel 60×40×23,4367
Пк2Front frame strutC-channel 60×40×22,1767
Х1Longitudinal brace (cross)C-channel 60×40×24,0694
Р1Purlin (rail)C-channel 60×40×26,0004
Р2Purlin (rail)C-channel 60×40×26,0004
Р3Purlin (rail)C-channel 60×40×26,0004
Р4Purlin (rail)C-channel 60×40×26,0004
Р5Purlin (rail)C-channel 60×40×21,3704
Р6Purlin (rail)C-channel 60×40×21,3704
—Bolt M10×100 / M10×25 set · frame and struts / purlins, braces, connectors——73
—Bolt M10×120 set · purlin to rafter——56
—Bolt M10×140 set · strut to post——7
—Bolt M10×150 set · post–rafter, strut to rafter — through spacer inserts——49
—Bolt M10×160 set · brace to post — through spacer inserts——8
—Bolt M10×200 set · strut to rafter — through spacer inserts——7
—Bolt M10×25 set · rafter splice (plate Н1)——28
—End clamp 30 mm——16
—Mid clamp (30–40 mm)——72
—Bolt M8×50 + channel nut——88
—Concrete for 21 posts, Ø500×1700——7.71 m³

Profile cutting

63 bars of 6,000 mm, 313.4 m of profile in total.

  • Tube 80×80×321 bars
  • C-channel 100×50×2.514 bars
  • C-channel 60×40×228 bars

Estimated cost

The engine's materials estimate for the median zone (Cherkasy).

Materials
176,581₴
With installation and delivery
238,446₴
Per 1 kW
9,772UAH/kW

Prices are the typical market prices built into the Solispec engine, as of 06.10.2026; no margin, no VAT.

All 26 lines of the engine's estimate, with prices
ItemQuantityPrice, UAHSum, UAH
Tube 80×80×3, stock length 6 000 mm21 bar42052,920
C-channel 100×50×2.5, stock length 6 000 mm14 bar38031,920
C-channel 60×40×2, stock length 6 000 mm28 bar23038,640
C-channel connector (splice plate L 300)16 pcs901,440
Bolt M10×100 cl. 8.8 set — frame, struts7 pcs22154
Bolt M10×25 cl. 8.8 set — purlins, braces, connectors89 pcs221,958
Bolt M10×120 cl. 8.8 set — purlin to rafter56 pcs271,512
Bolt M10×140 cl. 8.8 set — strut to post7 pcs27189
Bolt M10×150 cl. 8.8 set — post–rafter, strut to rafter — through spacer inserts49 pcs271,323
Bolt M10×160 cl. 8.8 set — brace to post — through spacer inserts8 pcs27216
Bolt M10×200 cl. 8.8 set — strut to rafter — through spacer inserts7 pcs27189
Bolt M10×25 cl. 8.8 set — rafter splice (plate Н1)28 pcs22616
End clamp 30 mm16 pcs35560
Mid clamp (30–40 mm)72 pcs322,304
Bolt M8×50 A2 + spring channel nut M897 pcs141,358
Post base anchor pin (M10 / rebar Ø12)21 pcs20420
Borehole casing (roofing felt / PVC, 300 mm)21 pcs601,260
Crushed stone 20–40 for the bottom of the boreholes0.41 m³900369
Earth electrode: 2 rods Ø16×1.5 m + strip 40×41 set1,5001,500
Wire PV-3 6 mm² green-yellow33 m351,155
Module earthing clip (under the clamp)40 pcs20800
Cable clip, stainless120 pcs5600
Zinc paint / cold galvanising spray 400 ml4 pcs3501,400
Concrete M200 for posts7.71 m³3,80029,298
Rebar Ø10 (4 bars per post)160 m284,480
Spacer inserts / packs — pieces of the same profile (from offcuts): 14 × 80 mm, 4 × 61 mm, 4 × 20 mm22 pcs00
Materials176,581

Yield

Yield: 1,139 kWh per 1 kW a year, ≈ 27,786 kWh a year in total (median zone, Cherkasy; tilt 30°, the optimum for the latitude is 35.3°).

A preliminary calculation; a design needs an engineer's check. Snow and wind per DBN V.1.2-2:2006 for the regional centre; profiles, footings and estimate by the Solispec engine 0.12.0.