Section of the table from the Solispec engine (median zone — Cherkasy)

Trina

Ground frame for 10 Trina Vertex N TSM-690NEG21C.20 panels (1×10)

1 row of 10 panels, 6.90 kW. The Solispec engine chose the profiles, the frame pitch and the footings for three snow and wind zones: Kherson has the lowest load of the regional centres, Cherkasy the median, Chernihiv the highest.

Power
6.90kW
Steel
262.6kg
Posts
14
Bolts
104
Materials
37,402₴
Yield
7,858kWh/year

Figures for the median zone (Cherkasy); all three zones are in the table below.

Ground frame designer

Open this frame in the builder

The builder opens with the Trina Vertex N TSM-690NEG21C.20 panel and the 1 × 10 layout; site — Cherkasy. Change the site, the tilt or the profiles and the checks and estimate are recalculated.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Three snow and wind zones

The same table designed for three regional centres: with the lowest, the median and the highest combined snow and wind load under DBN V.1.2-2:2006. For another site, open the frame in the builder.

ParameterLow loadKherson · S₀ 760 · W₀ 480Median loadCherkasy · S₀ 1,520 · W₀ 420High loadChernihiv · S₀ 1,720 · W₀ 410
PostsTube 60×60×2Tube 60×60×2Tube 60×60×2
RaftersTube 60×60×2Tube 60×60×2Tube 60×60×2
Purlins and bracesC-channel 60×40×2C-channel 60×40×2C-channel 60×40×2
Frames6 frames, pitch up to 2,520 mm7 frames, pitch up to 2,120 mm8 frames, pitch up to 1,830 mm
Posts121416
Footings (bored concrete)12 pcs, Ø300 mm, depth 900 mm14 pcs, Ø300 mm, depth 1,100 mm16 pcs, Ø300 mm, depth 1,300 mm
Concrete0.84 m³1.20 m³1.62 m³
Tilt30°30°30°
Panel bottom / post top600 / 1,339 mm600 / 1,339 mm600 / 1,339 mm
Panel field size13,350 × 1,460 mm13,350 × 1,460 mm13,350 × 1,460 mm
Row spacing between tables (no shade on 21 December)5,350 mm at noon · 6,020 mm ±2 h5,930 mm at noon · 6,850 mm ±2 h6,500 mm at noon · 7,720 mm ±2 h
Steel233.7 kg262.6 kg295.5 kg
BoltsM10 — 74, M8 — 22M10 — 82, M8 — 22M10 — 90, M8 — 22
Panel clampsend 4, middle 18end 4, middle 18end 4, middle 18
Materials32,153 UAH37,402 UAH41,344 UAH
With installation and delivery50,833 UAH56,077 UAH60,014 UAH
Per 1 kW7,367 UAH/kW8,127 UAH/kW8,698 UAH/kW
Yield1,266 kWh/kW · 8,738 kWh/year1,139 kWh/kW · 7,858 kWh/year1,043 kWh/kW · 7,198 kWh/year
Strength σ/fy98%97%78%
Deflection / (L/200)98%81%56%
Rafter strength11%13%12%
Post utilisation7%8%8%
Utilisation93%56%40%
Depth vs frost depthokokok
Checks overallwith a cautionwith a cautionpasses

Checks and cautions

Member utilisation as the engine computes it. Cautions are checks that pass, but with a small margin.

  • Max. frame pitch, mmThe purlins between the frames are used above 80 % (strength or deflection): the structure passes, but the margin is small. A shorter frame pitch or a deeper purlin gives more margin.Kherson: Frame spacing 2 520 mm, 6 frames. Purlin C-channel 60×40×2: strength 98%, deflection 98% of L/200 (snow on panel 489 Pa).Cherkasy: Frame spacing 2 120 mm, 7 frames. Purlin C-channel 60×40×2: strength 97%, deflection 81% of L/200 (snow on panel 977 Pa).
  • Embedment, mmThe footing resists wind uplift at above 80 % utilisation, or it is shallower than the frost depth. The soil resistance in the calculation is an estimate — check the soil on site.Kherson: Foundation Ø300 × 900: 0.064 m³ of concrete per post. Wind uplift on the front post ≈ 7.2 kN (with γ=1.5) vs ≈ 7.7 kN (concrete weight + soil friction, estimate) → 93%.

Bill of materials

The parts of one table for the median zone (Cherkasy): mark, name, profile, cut length, quantity.

MarkPartProfileLength, mmQuantity
П1Front postTube 60×60×22,0227
П2Rear postTube 60×60×22,4647
Кр1Rafter (inclined beam)Tube 60×60×21,5247
Пк1Frame strutC-channel 60×40×29997
Х1Longitudinal brace (cross)C-channel 60×40×22,2644
Р1Purlin (rail)C-channel 60×40×26,0001
Р2Purlin (rail)C-channel 60×40×26,0001
Р3Purlin (rail)C-channel 60×40×26,0001
Р4Purlin (rail)C-channel 60×40×26,0001
Р5Purlin (rail)C-channel 60×40×21,3501
Р6Purlin (rail)C-channel 60×40×21,3501
—Bolt M10×140 / M10×80 set · frame and struts / purlins, braces, connectors——67
—Bolt M10×150 set · brace to post, strut to rafter — through spacer inserts——15
—End clamp 33 mm——4
—Mid clamp (30–40 mm)——18
—Bolt M8×50 + channel nut——22
—Concrete for 14 posts, Ø300×1100——1.20 m³

Profile cutting

17 bars of 6,000 mm, 84.8 m of profile in total.

  • Tube 60×60×29 bars
  • C-channel 60×40×28 bars

Estimated cost

The engine's materials estimate for the median zone (Cherkasy).

Materials
37,402₴
With installation and delivery
56,077₴
Per 1 kW
8,127UAH/kW

Prices are the typical market prices built into the Solispec engine, as of 06.10.2026; no margin, no VAT.

All 20 lines of the engine's estimate, with prices
ItemQuantityPrice, UAHSum, UAH
Tube 60×60×2, stock length 6 000 mm9 bar21011,340
C-channel 60×40×2, stock length 6 000 mm8 bar23011,040
C-channel connector (splice plate L 300)4 pcs90360
Bolt M10×140 cl. 8.8 set — frame, struts44 pcs22968
Bolt M10×80 cl. 8.8 set — purlins, braces, connectors32 pcs22704
Bolt M10×150 cl. 8.8 set — strut to rafter, brace to post — through spacer inserts15 pcs27405
End clamp 33 mm4 pcs35140
Mid clamp (30–40 mm)18 pcs32576
Bolt M8×50 A2 + spring channel nut M825 pcs14350
Post base anchor pin (M10 / rebar Ø12)14 pcs20280
Borehole casing (roofing felt / PVC, 300 mm)14 pcs60840
Crushed stone 20–40 for the bottom of the boreholes0.10 m³90090
Earth electrode: 2 rods Ø16×1.5 m + strip 40×41 set1,5001,500
Wire PV-3 6 mm² green-yellow33 m351,155
Module earthing clip (under the clamp)10 pcs20200
Cable clip, stainless30 pcs5150
Zinc paint / cold galvanising spray 400 ml2 pcs350700
Concrete M200 for posts1.20 m³3,8004,560
Rebar Ø10 (4 bars per post)73 m282,044
Spacer inserts / packs — pieces of the same profile (from offcuts): 4 × 71 mm, 7 × 70 mm, 4 × 30 mm, 7 × 10 mm22 pcs00
Materials37,402

Yield

Yield: 1,139 kWh per 1 kW a year, ≈ 7,858 kWh a year in total (median zone, Cherkasy; tilt 30°, the optimum for the latitude is 35.3°).

A preliminary calculation; a design needs an engineer's check. Snow and wind per DBN V.1.2-2:2006 for the regional centre; profiles, footings and estimate by the Solispec engine 0.12.0.