Section of the table from the Solispec engine (median zone — Cherkasy)

Trina

Ground frame for 24 Trina Vertex N TSM-690NEG21C.20 panels (2×12)

2 rows of 12 panels, 16.56 kW. The Solispec engine chose the profiles, the frame pitch and the footings for three snow and wind zones: Kherson has the lowest load of the regional centres, Cherkasy the median, Chernihiv the highest.

Power
16.56kW
Steel
507.3kg
Posts
18
Bolts
184
Materials
71,062₴
Yield
18,858kWh/year

Figures for the median zone (Cherkasy); all three zones are in the table below.

Ground frame designer

Open this frame in the builder

The builder opens with the Trina Vertex N TSM-690NEG21C.20 panel and the 2 × 12 layout; site — Cherkasy. Change the site, the tilt or the profiles and the checks and estimate are recalculated.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Three snow and wind zones

The same table designed for three regional centres: with the lowest, the median and the highest combined snow and wind load under DBN V.1.2-2:2006. For another site, open the frame in the builder.

ParameterLow loadKherson · S₀ 760 · W₀ 480Median loadCherkasy · S₀ 1,520 · W₀ 420High loadChernihiv · S₀ 1,720 · W₀ 410
PostsTube 60×60×2Tube 60×60×2Tube 60×60×2
RaftersC-channel 60×40×2C-channel 80×40×2C-channel 80×40×2
Purlins and bracesC-channel 60×40×2C-channel 60×40×2C-channel 60×40×2
Frames9 frames, pitch up to 1,930 mm9 frames, pitch up to 1,930 mm9 frames, pitch up to 1,930 mm
Posts181818
Footings (bored concrete)18 pcs, Ø400 mm, depth 1,100 mm18 pcs, Ø350 mm, depth 1,100 mm18 pcs, Ø300 mm, depth 1,300 mm
Concrete2.74 m³2.10 m³1.82 m³
Tilt30°30°30°
Panel bottom / post top600 / 2,289 mm600 / 2,280 mm600 / 2,280 mm
Panel field size15,996 × 3,105 mm15,996 × 3,110 mm15,996 × 3,110 mm
Row spacing between tables (no shade on 21 December)10,740 mm at noon · 12,080 mm ±2 h11,900 mm at noon · 13,750 mm ±2 h13,050 mm at noon · 15,510 mm ±2 h
Steel511.7 kg507.3 kg520.3 kg
BoltsM10 — 132, M8 — 52M10 — 132, M8 — 52M10 — 132, M8 — 52
Panel clampsend 8, middle 44end 8, middle 44end 8, middle 44
Materials69,168 UAH71,062 UAH76,654 UAH
With installation and delivery111,508 UAH113,402 UAH118,994 UAH
Per 1 kW6,734 UAH/kW6,848 UAH/kW7,186 UAH/kW
Yield1,266 kWh/kW · 20,972 kWh/year1,139 kWh/kW · 18,858 kWh/year1,043 kWh/kW · 17,274 kWh/year
Strength σ/fy62%84%90%
Deflection / (L/200)47%64%68%
Rafter strength91%84%90%
Post utilisation18%24%26%
Utilisation96%99%98%
Depth vs frost depthokokok
Checks overallwith a cautionwith a cautionwith a caution

Checks and cautions

Member utilisation as the engine computes it. Cautions are checks that pass, but with a small margin.

  • Rafter profileThe rafter is used above 80 %, or the frame's posts stand far apart: the structure passes, but the margin is small.Kherson: Rafter C-channel 60×40×2: span between posts 2 278, cantilever 825 mm → strength 91%.Cherkasy: Rafter C-channel 80×40×2: span between posts 2 278, cantilever 825 mm → strength 84%.Chernihiv: Rafter C-channel 80×40×2: span between posts 2 278, cantilever 825 mm → strength 90%.
  • Embedment, mmThe footing resists wind uplift at above 80 % utilisation, or it is shallower than the frost depth. The soil resistance in the calculation is an estimate — check the soil on site.Kherson: Foundation Ø400 × 1 100: 0.138 m³ of concrete per post. Wind uplift on the front post ≈ 12.8 kN (with γ=1.5) vs ≈ 13.4 kN (concrete weight + soil friction, estimate) → 96%.Cherkasy: Foundation Ø350 × 1 100: 0.106 m³ of concrete per post. Wind uplift on the front post ≈ 11.2 kN (with γ=1.5) vs ≈ 11.4 kN (concrete weight + soil friction, estimate) → 99%.Chernihiv: Foundation Ø300 × 1 300: 0.092 m³ of concrete per post. Wind uplift on the front post ≈ 10.9 kN (with γ=1.5) vs ≈ 11.2 kN (concrete weight + soil friction, estimate) → 98%.
  • Max. frame pitch, mmThe purlins between the frames are used above 80 % (strength or deflection): the structure passes, but the margin is small. A shorter frame pitch or a deeper purlin gives more margin.Cherkasy: Frame spacing 1 930 mm, 9 frames. Purlin C-channel 60×40×2: strength 84%, deflection 64% of L/200 (snow on panel 977 Pa).Chernihiv: Frame spacing 1 930 mm, 9 frames. Purlin C-channel 60×40×2: strength 90%, deflection 68% of L/200 (snow on panel 1 106 Pa).

Bill of materials

The parts of one table for the median zone (Cherkasy): mark, name, profile, cut length, quantity.

MarkPartProfileLength, mmQuantity
П1Front postTube 60×60×22,2669
П2Rear postTube 60×60×23,4059
Кр1Rafter (inclined beam)C-channel 80×40×23,9289
Пк1Frame strutC-channel 60×40×21,8129
Х1Longitudinal brace (cross)C-channel 60×40×22,5444
Р1Purlin (rail)C-channel 60×40×26,0002
Р2Purlin (rail)C-channel 60×40×26,0002
Р3Purlin (rail)C-channel 60×40×26,0002
Р4Purlin (rail)C-channel 60×40×26,0002
Р5Purlin (rail)C-channel 60×40×23,9962
Р6Purlin (rail)C-channel 60×40×23,9962
—Bolt M10×25 set · purlins, braces, connectors——34
—Bolt M10×90 set · strut to post — through spacer inserts——9
—Bolt M10×100 set · purlin to rafter——36
—Bolt M10×130 set · post–rafter — through spacer inserts——36
—Bolt M10×140 set · strut to rafter — through spacer inserts——9
—Bolt M10×150 set · brace to post — through spacer inserts——8
—End clamp 33 mm——8
—Mid clamp (30–40 mm)——44
—Bolt M8×50 + channel nut——52
—Concrete for 18 posts, Ø350×1100——2.10 m³

Profile cutting

34 bars of 6,000 mm, 176.9 m of profile in total.

  • Tube 60×60×29 bars
  • C-channel 80×40×29 bars
  • C-channel 60×40×216 bars

Estimated cost

The engine's materials estimate for the median zone (Cherkasy).

Materials
71,062₴
With installation and delivery
113,402₴
Per 1 kW
6,848UAH/kW

The engine's estimate has 24 lines; the full list is in the builder. Prices are the typical market prices built into the Solispec engine, as of 06.10.2026; no margin, no VAT.

Yield

Yield: 1,139 kWh per 1 kW a year, ≈ 18,858 kWh a year in total (median zone, Cherkasy; tilt 30°, the optimum for the latitude is 35.3°).

A preliminary calculation; a design needs an engineer's check. Snow and wind per DBN V.1.2-2:2006 for the regional centre; profiles, footings and estimate by the Solispec engine 0.12.0.