Solar plant: site data
Solar power plant in Kosmach, Kosivskyi Raion, Ivano-Frankivsk Oblast
Kosmach: 1,076 kWh per kWp a year, tilt 40° 11° east of south (PVGIS). 1.9% below the oblast median (1,097). #27 of 41 in the rayon, #519 of 700 in the oblast.
Kosiv, the rayon centre, is 21 km away. 614 m above sea level — above 500 m the DBN snow and wind are higher. 21 km away: Kosiv, the nearest bigger centre, 1,110 — 3.1% less here. Snow and wind from the nearest regional centre in the DBN — Івано-Франківськ, 66 km. 11.43 m between rows, pitch 15.09 m (latitude 48.3°).
- Yield of 1 kWp
- 1,076kWh/year
- Tilt
- 40°11° east of south
- 10 kW
- 10,757kWh/year
- Row pitch
- 15.09m · GCR 0.32
- T_min
- -38 °Cregion IIIA, Carpathian
- Snow S₀ / wind W₀
- 1,410 / 500Pa
Ground frame designer
A ground frame for a solar plant: Kosmach
The designer opens with this place’s coordinates, latitude 48.3° for the row spacing and the DBN loads of the nearest regional centre — Івано-Франківськ, 66 km: snow 1,410 Pa, wind 500 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
July: 120 kWh/kWp, December: 46 — 2.6 times less.
November: 60 against 48 in the oblast, 25.0% more.
| kWp | A year | July | December |
|---|---|---|---|
| 5 | 5,379 | 600 | 230 |
| 10 | 10,757 | 1,200 | 460 |
| 15 | 16,136 | 1,800 | 690 |
Snow and wind: Івано-Франківськ
Example: a 10 kW ground frame
For the loads of Ivano-Frankivsk: 11.16 kWp, 18 panels, 410 kg of steel, 16 piles, materials ≈ 54,212 UAH.
How these numbers are computed
Nearby
- Pochosa3 km1,062 kWh/kWp
- Akreshory3 km1,071 kWh/kWp
- Brustury6 km1,071 kWh/kWp
- Tekuche6 km1,081 kWh/kWp
- Prokurava6 km1,073 kWh/kWp
- Shepit8 km1,027 kWh/kWp
All places: Kosivskyi RaionIvano-Frankivsk Oblast: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.