Solar plant: site data

Solar power plant in Skelivka, Cherkaskyi Raion, Cherkasy Oblast

Skelivka: 1,159 kWh per kWp a year, tilt 37° 2° east of south (PVGIS). 1.3% above the oblast median (1,144). #37 of 207 in the rayon, #79 of 731 in the oblast.

Cherkasy, the rayon centre, is 44 km away. 161 m above sea level. 14 km away: Oleksandrivka, the nearest bigger centre, 1,152 — 0.7% more here. Snow and wind from the nearest regional centre in the DBN — Черкаси, 43 km. 11.29 m between rows, pitch 15.11 m (latitude 49.1°).

Yield of 1 kWp
1,159kWh/year
Tilt
37°2° east of south
10 kW
11,594kWh/year
Row pitch
15.11m · GCR 0.32
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,520 / 420Pa

Ground frame designer

A ground frame for a solar plant: Skelivka

The designer opens with this place’s coordinates, latitude 49.1° for the row spacing and the DBN loads of the nearest regional centre — Черкаси, 43 km: snow 1,520 Pa, wind 420 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

38Jan57Feb96Mar120Apr140May143Jun148Jul145Aug118Sep88Oct40Nov28Dec

July: 148 kWh/kWp, December: 28 — 5.3 times less.

January: 38 against 35 in the oblast, 8.6% more.

Skelivka: plants, kWh
kWpA yearJulyDecember
55,797740140
1011,5941,480280
1517,3912,220420

Snow and wind: Черкаси

Example: a 10 kW ground frame

For the loads of Cherkasy: 11.16 kWp, 18 panels, 372 kg of steel, 12 piles, materials ≈ 49,705 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed