Section of the table from the Solispec engine (median zone — Cherkasy)

Leapton

Ground frame for 30 Leapton LP210*210-M-66-NB 700W panels (3×10)

3 rows of 10 panels, 21.00 kW. The Solispec engine chose the profiles, the frame pitch and the footings for three snow and wind zones: Kherson has the lowest load of the regional centres, Cherkasy the median, Chernihiv the highest.

Power
21.00kW
Steel
851.9kg
Posts
18
Bolts
286
Materials
111,256₴
Yield
23,914kWh/year

Figures for the median zone (Cherkasy); all three zones are in the table below.

Ground frame designer

Open this frame in the builder

The builder opens with the Leapton LP210*210-M-66-NB 700W panel and the 3 × 10 layout; site — Cherkasy. Change the site, the tilt or the profiles and the checks and estimate are recalculated.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Three snow and wind zones

The same table designed for three regional centres: with the lowest, the median and the highest combined snow and wind load under DBN V.1.2-2:2006. For another site, open the frame in the builder.

ParameterLow loadKherson · S₀ 760 · W₀ 480Median loadCherkasy · S₀ 1,520 · W₀ 420High loadChernihiv · S₀ 1,720 · W₀ 410
PostsTube 60×60×2Tube 60×60×2Tube 60×60×2
RaftersC-channel 100×50×2.5C-channel 100×50×2.5C-channel 100×50×2.5
Purlins and bracesC-channel 60×40×2C-channel 60×40×2C-channel 41×41×2.5
Frames7 frames, pitch up to 2,120 mm9 frames, pitch up to 1,610 mm10 frames, pitch up to 1,440 mm
Posts141820
Footings (bored concrete)14 pcs, Ø500 mm, depth 1,500 mm18 pcs, Ø400 mm, depth 1,300 mm20 pcs, Ø350 mm, depth 1,500 mm
Concrete4.54 m³3.24 m³3.18 m³
Tilt30°30°30°
Panel bottom / post top600 / 3,221 mm600 / 3,221 mm600 / 3,237 mm
Panel field size13,350 × 4,759 mm13,350 × 4,759 mm13,350 × 4,750 mm
Row spacing between tables (no shade on 21 December)16,130 mm at noon · 18,140 mm ±2 h17,880 mm at noon · 20,650 mm ±2 h19,600 mm at noon · 23,290 mm ±2 h
Steel729.2 kg851.9 kg935.4 kg
BoltsM10 — 184, M8 — 66M10 — 220, M8 — 66M10 — 238, M8 — 66
Panel clampsend 12, middle 54end 12, middle 54end 12, middle 54
Materials101,869 UAH111,256 UAH114,834 UAH
With installation and delivery155,396 UAH164,538 UAH168,014 UAH
Per 1 kW7,400 UAH/kW7,835 UAH/kW8,001 UAH/kW
Yield1,266 kWh/kW · 26,595 kWh/year1,139 kWh/kW · 23,914 kWh/year1,043 kWh/kW · 21,906 kWh/year
Strength σ/fy79%60%93%
Deflection / (L/200)66%38%66%
Rafter strength95%96%92%
Post utilisation49%50%48%
Utilisation98%99%88%
Depth vs frost depthokokok
Bolt utilisation28%29%28%
Plate section6%6%6%
Not includedengineer to checkengineer to checkengineer to check
Checks overallwith a cautionwith a cautionwith a caution

Checks and cautions

Member utilisation as the engine computes it. Cautions are checks that pass, but with a small margin.

  • Rafter profileThe rafter is used above 80 %, or the frame's posts stand far apart: the structure passes, but the margin is small.Kherson: Rafter C-channel 100×50×2.5: span between posts 3 673, cantilever 1 330 mm → strength 95%.Cherkasy: Rafter C-channel 100×50×2.5: span between posts 3 673, cantilever 1 330 mm → strength 96%.Chernihiv: Rafter C-channel 100×50×2.5: span between posts 3 673, cantilever 1 330 mm → strength 92%.
  • Embedment, mmThe footing resists wind uplift at above 80 % utilisation, or it is shallower than the frost depth. The soil resistance in the calculation is an estimate — check the soil on site.Kherson: Foundation Ø500 × 1 500: 0.295 m³ of concrete per post. Wind uplift on the front post ≈ 23.5 kN (with γ=1.5) vs ≈ 24.0 kN (concrete weight + soil friction, estimate) → 98%.Cherkasy: Foundation Ø400 × 1 300: 0.163 m³ of concrete per post. Wind uplift on the front post ≈ 15.6 kN (with γ=1.5) vs ≈ 15.8 kN (concrete weight + soil friction, estimate) → 99%.Chernihiv: Foundation Ø350 × 1 500: 0.144 m³ of concrete per post. Wind uplift on the front post ≈ 13.6 kN (with γ=1.5) vs ≈ 15.5 kN (concrete weight + soil friction, estimate) → 88%.
  • Stock length, mmKherson: Rafter 6 332 mm is longer than the 6 000 mm stock length — 2 pieces: Кр1а 6 000, Кр1б 332 mm. Splice — plate Н1 L 300 mm of the same profile, back to back, 2+2 bolts M10 cl. 8.8, at 6 000 mm from the lower end of the rafter, where the moment is small. Bolt: 5.12 kN vs 18.00 kN (28%), plate 6%. Rafter splice — engineer to check: the plate's eccentricity, the C-channel's torsion and the axial force are not included.Cherkasy: Rafter 6 332 mm is longer than the 6 000 mm stock length — 2 pieces: Кр1а 6 000, Кр1б 332 mm. Splice — plate Н1 L 300 mm of the same profile, back to back, 2+2 bolts M10 cl. 8.8, at 6 000 mm from the lower end of the rafter, where the moment is small. Bolt: 5.18 kN vs 18.00 kN (29%), plate 6%. Rafter splice — engineer to check: the plate's eccentricity, the C-channel's torsion and the axial force are not included.Chernihiv: Rafter 6 332 mm is longer than the 6 000 mm stock length — 2 pieces: Кр1а 6 000, Кр1б 332 mm. Splice — plate Н1 L 300 mm of the same profile, back to back, 2+2 bolts M10 cl. 8.8, at 6 000 mm from the lower end of the rafter, where the moment is small. Bolt: 4.96 kN vs 18.00 kN (28%), plate 6%. Rafter splice — engineer to check: the plate's eccentricity, the C-channel's torsion and the axial force are not included.
  • Max. frame pitch, mmThe purlins between the frames are used above 80 % (strength or deflection): the structure passes, but the margin is small. A shorter frame pitch or a deeper purlin gives more margin.Chernihiv: Frame spacing 1 440 mm, 10 frames. Purlin C-channel 41×41×2.5: strength 93%, deflection 66% of L/200 (snow on panel 1 106 Pa).

Bill of materials

The parts of one table for the median zone (Cherkasy): mark, name, profile, cut length, quantity.

MarkPartProfileLength, mmQuantity
П1Front postTube 60×60×22,7109
П2Rear postTube 60×60×24,5469
Кр1аRafter (inclined beam)C-channel 100×50×2.56,0009
Кр1бRafter (inclined beam)C-channel 100×50×2.53329
Н1Rafter splice plateC-channel 100×50×2.53009
Пк1Frame strutC-channel 60×40×22,6479
Пк2Front frame strutC-channel 60×40×23,5149
Х1Longitudinal brace (cross)C-channel 60×40×23,0414
Р1Purlin (rail)C-channel 60×40×26,0003
Р2Purlin (rail)C-channel 60×40×26,0003
Р3Purlin (rail)C-channel 60×40×26,0003
Р4Purlin (rail)C-channel 60×40×26,0003
Р5Purlin (rail)C-channel 60×40×21,3503
Р6Purlin (rail)C-channel 60×40×21,3503
—Bolt M10×80 / M10×25 set · frame and struts / purlins, braces, connectors——59
—Bolt M10×90 set · strut to post — through spacer inserts——9
—Bolt M10×120 set · purlin to rafter——54
—Bolt M10×130 set · post–rafter, strut to post — through spacer inserts——45
—Bolt M10×140 set · strut to rafter — through spacer inserts——9
—Bolt M10×150 set · brace to post — through spacer inserts——8
—Bolt M10×25 set · rafter splice (plate Н1)——36
—End clamp 33 mm——12
—Mid clamp (30–40 mm)——54
—Bolt M8×50 + channel nut——66
—Concrete for 18 posts, Ø400×1300——3.23 m³

Profile cutting

52 bars of 6,000 mm, 272.7 m of profile in total.

  • Tube 60×60×214 bars
  • C-channel 100×50×2.510 bars
  • C-channel 60×40×228 bars

Estimated cost

The engine's materials estimate for the median zone (Cherkasy).

Materials
111,256₴
With installation and delivery
164,538₴
Per 1 kW
7,835UAH/kW

Prices are the typical market prices built into the Solispec engine, as of 06.10.2026; no margin, no VAT.

All 26 lines of the engine's estimate, with prices
ItemQuantityPrice, UAHSum, UAH
Tube 60×60×2, stock length 6 000 mm14 bar21017,640
C-channel 100×50×2.5, stock length 6 000 mm10 bar38022,800
C-channel 60×40×2, stock length 6 000 mm28 bar23038,640
C-channel connector (splice plate L 300)12 pcs901,080
Bolt M10×80 cl. 8.8 set — frame, struts9 pcs22198
Bolt M10×25 cl. 8.8 set — purlins, braces, connectors50 pcs221,100
Bolt M10×90 cl. 8.8 set — strut to post — through spacer inserts9 pcs27243
Bolt M10×120 cl. 8.8 set — purlin to rafter77 pcs272,079
Bolt M10×130 cl. 8.8 set — post–rafter, strut to post — through spacer inserts45 pcs271,215
Bolt M10×140 cl. 8.8 set — strut to rafter — through spacer inserts9 pcs27243
Bolt M10×150 cl. 8.8 set — brace to post — through spacer inserts8 pcs27216
Bolt M10×25 cl. 8.8 set — rafter splice (plate Н1)36 pcs22792
End clamp 33 mm12 pcs35420
Mid clamp (30–40 mm)54 pcs321,728
Bolt M8×50 A2 + spring channel nut M873 pcs141,022
Post base anchor pin (M10 / rebar Ø12)18 pcs20360
Borehole casing (roofing felt / PVC, 300 mm)18 pcs601,080
Crushed stone 20–40 for the bottom of the boreholes0.23 m³900207
Earth electrode: 2 rods Ø16×1.5 m + strip 40×41 set1,5001,500
Wire PV-3 6 mm² green-yellow37 m351,295
Module earthing clip (under the clamp)30 pcs20600
Cable clip, stainless90 pcs5450
Zinc paint / cold galvanising spray 400 ml3 pcs3501,050
Concrete M200 for posts3.23 m³3,80012,274
Rebar Ø10 (4 bars per post)108 m283,024
Spacer inserts / packs — pieces of the same profile (from offcuts): 4 × 71 mm, 9 × 70 mm, 9 × 50 mm, 4 × 30 mm, 9 × 10 mm35 pcs00
Materials111,256

Yield

Yield: 1,139 kWh per 1 kW a year, ≈ 23,914 kWh a year in total (median zone, Cherkasy; tilt 30°, the optimum for the latitude is 35.3°).

A preliminary calculation; a design needs an engineer's check. Snow and wind per DBN V.1.2-2:2006 for the regional centre; profiles, footings and estimate by the Solispec engine 0.12.0.

Other layouts of this panel

The 3×10 layout with other panels

Next