Section of the table from the Solispec engine (median zone — Cherkasy)

Aiko

Ground frame for 12 Aiko Neostar 2P AIKO-A460-MAH54Mw panels (2×6)

2 rows of 6 panels, 5.52 kW. The Solispec engine chose the profiles, the frame pitch and the footings for three snow and wind zones: Kherson has the lowest load of the regional centres, Cherkasy the median, Chernihiv the highest.

Power
5.52kW
Steel
229.1kg
Posts
8
Bolts
94
Materials
29,439₴
Yield
6,286kWh/year

Figures for the median zone (Cherkasy); all three zones are in the table below.

Ground frame designer

Open this frame in the builder

The builder opens with the Aiko Neostar 2P AIKO-A460-MAH54Mw panel and the 2 × 6 layout; site — Cherkasy. Change the site, the tilt or the profiles and the checks and estimate are recalculated.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Three snow and wind zones

The same table designed for three regional centres: with the lowest, the median and the highest combined snow and wind load under DBN V.1.2-2:2006. For another site, open the frame in the builder.

ParameterLow loadKherson · S₀ 760 · W₀ 480Median loadCherkasy · S₀ 1,520 · W₀ 420High loadChernihiv · S₀ 1,720 · W₀ 410
PostsTube 60×60×2Tube 60×60×2Tube 60×60×2
RaftersTube 60×60×2Tube 60×60×2Tube 60×60×2
Purlins and bracesC-channel 41×41×2.5C-channel 60×40×2C-channel 60×40×2
Frames5 frames, pitch up to 1,640 mm4 frames, pitch up to 2,130 mm4 frames, pitch up to 2,130 mm
Posts1088
Footings (bored concrete)10 pcs, Ø300 mm, depth 900 mm8 pcs, Ø300 mm, depth 1,100 mm8 pcs, Ø300 mm, depth 1,300 mm
Concrete0.70 m³0.68 m³0.81 m³
Tilt30°30°30°
Panel bottom / post top600 / 1,850 mm600 / 1,834 mm600 / 1,834 mm
Panel field size7,044 × 2,308 mm7,044 × 2,317 mm7,044 × 2,317 mm
Row spacing between tables (no shade on 21 December)7,930 mm at noon · 8,920 mm ±2 h8,790 mm at noon · 10,150 mm ±2 h9,630 mm at noon · 11,450 mm ±2 h
Steel251.0 kg229.1 kg234.8 kg
BoltsM10 — 76, M8 — 28M10 — 66, M8 — 28M10 — 66, M8 — 28
Panel clampsend 8, middle 20end 8, middle 20end 8, middle 20
Materials30,227 UAH29,439 UAH30,101 UAH
With installation and delivery45,462 UAH44,701 UAH45,363 UAH
Per 1 kW8,236 UAH/kW8,098 UAH/kW8,218 UAH/kW
Yield1,266 kWh/kW · 6,991 kWh/year1,139 kWh/kW · 6,286 kWh/year1,043 kWh/kW · 5,758 kWh/year
Strength σ/fy57%73%79%
Deflection / (L/200)46%61%66%
Rafter strength28%49%53%
Post utilisation9%15%17%
Utilisation96%89%74%
Depth vs frost depthokokok
Checks overallwith a cautionwith a cautionpasses

Checks and cautions

Member utilisation as the engine computes it. Cautions are checks that pass, but with a small margin.

  • Embedment, mmThe footing resists wind uplift at above 80 % utilisation, or it is shallower than the frost depth. The soil resistance in the calculation is an estimate — check the soil on site.Kherson: Foundation Ø300 × 900: 0.064 m³ of concrete per post. Wind uplift on the front post ≈ 7.4 kN (with γ=1.5) vs ≈ 7.7 kN (concrete weight + soil friction, estimate) → 96%.Cherkasy: Foundation Ø300 × 1 100: 0.078 m³ of concrete per post. Wind uplift on the front post ≈ 8.4 kN (with γ=1.5) vs ≈ 9.5 kN (concrete weight + soil friction, estimate) → 89%.

Bill of materials

The parts of one table for the median zone (Cherkasy): mark, name, profile, cut length, quantity.

MarkPartProfileLength, mmQuantity
П1Front postTube 60×60×22,1024
П2Rear postTube 60×60×22,9594
Кр1Rafter (inclined beam)Tube 60×60×22,9544
Пк1Frame strutC-channel 60×40×21,4234
Х1Longitudinal brace (cross)C-channel 60×40×22,4634
Р1Purlin (rail)C-channel 60×40×26,0002
Р2Purlin (rail)C-channel 60×40×26,0002
Р3Purlin (rail)C-channel 60×40×21,0442
Р4Purlin (rail)C-channel 60×40×21,0442
—Bolt M10×140 / M10×80 set · frame and struts / purlins, braces, connectors——54
—Bolt M10×150 set · brace to post, strut to rafter — through spacer inserts——12
—End clamp 30 mm——8
—Mid clamp (30–40 mm)——20
—Bolt M8×50 + channel nut——28
—Concrete for 8 posts, Ø300×1100——0.68 m³

Profile cutting

14 bars of 6,000 mm, 75.8 m of profile in total.

  • Tube 60×60×26 bars
  • C-channel 60×40×28 bars

Estimated cost

The engine's materials estimate for the median zone (Cherkasy).

Materials
29,439₴
With installation and delivery
44,701₴
Per 1 kW
8,098UAH/kW

Prices are the typical market prices built into the Solispec engine, as of 06.10.2026; no margin, no VAT.

All 20 lines of the engine's estimate, with prices
ItemQuantityPrice, UAHSum, UAH
Tube 60×60×2, stock length 6 000 mm6 bar2107,560
C-channel 60×40×2, stock length 6 000 mm8 bar23011,040
C-channel connector (splice plate L 300)4 pcs90360
Bolt M10×140 cl. 8.8 set — frame, struts20 pcs22440
Bolt M10×80 cl. 8.8 set — purlins, braces, connectors41 pcs22902
Bolt M10×150 cl. 8.8 set — strut to rafter, brace to post — through spacer inserts12 pcs27324
End clamp 30 mm8 pcs35280
Mid clamp (30–40 mm)20 pcs32640
Bolt M8×50 A2 + spring channel nut M831 pcs14434
Post base anchor pin (M10 / rebar Ø12)8 pcs20160
Borehole casing (roofing felt / PVC, 300 mm)8 pcs60480
Crushed stone 20–40 for the bottom of the boreholes0.06 m³90054
Earth electrode: 2 rods Ø16×1.5 m + strip 40×41 set1,5001,500
Wire PV-3 6 mm² green-yellow21 m35735
Module earthing clip (under the clamp)12 pcs20240
Cable clip, stainless36 pcs5180
Zinc paint / cold galvanising spray 400 ml1 pcs350350
Concrete M200 for posts0.68 m³3,8002,584
Rebar Ø10 (4 bars per post)42 m281,176
Spacer inserts / packs — pieces of the same profile (from offcuts): 4 × 71 mm, 4 × 70 mm, 4 × 30 mm, 4 × 10 mm16 pcs00
Materials29,439

Yield

Yield: 1,139 kWh per 1 kW a year, ≈ 6,286 kWh a year in total (median zone, Cherkasy; tilt 30°, the optimum for the latitude is 35.3°).

A preliminary calculation; a design needs an engineer's check. Snow and wind per DBN V.1.2-2:2006 for the regional centre; profiles, footings and estimate by the Solispec engine 0.12.0.

Other layouts of this panel

The 2×6 layout with other panels

Next