Solar plant: site data
Solar power plant in Tatariv, Nadvirnianskyi Raion, Ivano-Frankivsk Oblast
Tatariv: 965 kWh per kWp a year, tilt 35° 10° west of south (PVGIS). 12.1% below the oblast median (1,097). #57 of 58 in the rayon, #692 of 700 in the oblast.
Nadvirna, the rayon centre, is 33 km away. 685 m above sea level — above 500 m the DBN snow and wind are higher. 28 km away: Verkhovyna, the nearest bigger centre, 1,074 — 10.2% less here. Snow and wind from the nearest regional centre in the DBN — Івано-Франківськ, 65 km. 10.20 m between rows, pitch 14.12 m (latitude 48.3°).
- Yield of 1 kWp
- 965kWh/year
- Tilt
- 35°10° west of south
- 10 kW
- 9,646kWh/year
- Row pitch
- 14.12m · GCR 0.34
- T_min
- -38 °Cregion IIIA, Carpathian
- Snow S₀ / wind W₀
- 1,410 / 500Pa
Ground frame designer
A ground frame for a solar plant: Tatariv
The designer opens with this place’s coordinates, latitude 48.3° for the row spacing and the DBN loads of the nearest regional centre — Івано-Франківськ, 65 km: snow 1,410 Pa, wind 500 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
July: 118 kWh/kWp, December: 27 — 4.4 times less.
December: 27 against 38 in the oblast, 28.9% less.
| kWp | A year | July | December |
|---|---|---|---|
| 5 | 4,823 | 590 | 135 |
| 10 | 9,646 | 1,180 | 270 |
| 15 | 14,469 | 1,770 | 405 |
Snow and wind: Івано-Франківськ
Example: a 10 kW ground frame
For the loads of Ivano-Frankivsk: 11.16 kWp, 18 panels, 410 kg of steel, 16 piles, materials ≈ 54,212 UAH.
How these numbers are computed
Nearby
- Vorokhta5 km1,053 kWh/kWp
- Yablunytsia8 km1,092 kWh/kWp
- Voronenko8 km1,049 kWh/kWp
- Mykulychyn8 km1,063 kWh/kWp
- Polianytsia11 km1,044 kWh/kWp
- Yaremche12 km1,040 kWh/kWp
All places: Nadvirnianskyi RaionIvano-Frankivsk Oblast: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.