Solar plant: site data
Solar power plant in Mykulychyn, Nadvirnianskyi Raion, Ivano-Frankivsk Oblast
Mykulychyn: 1,063 kWh per kWp a year, tilt 40° 10° east of south (PVGIS). 3.1% below the oblast median (1,097). #32 of 58 in the rayon, #579 of 700 in the oblast.
Nadvirna, the rayon centre, is 25 km away. 621 m above sea level — above 500 m the DBN snow and wind are higher. 25 km away: Nadvirna, the nearest bigger centre, 1,085 — 2.0% less here. Snow and wind from the nearest regional centre in the DBN — Івано-Франківськ, 57 km. 11.49 m between rows, pitch 15.15 m (latitude 48.4°).
- Yield of 1 kWp
- 1,063kWh/year
- Tilt
- 40°10° east of south
- 10 kW
- 10,633kWh/year
- Row pitch
- 15.15m · GCR 0.32
- T_min
- -38 °Cregion IIIA, Carpathian
- Snow S₀ / wind W₀
- 1,410 / 500Pa
Ground frame designer
A ground frame for a solar plant: Mykulychyn
The designer opens with this place’s coordinates, latitude 48.4° for the row spacing and the DBN loads of the nearest regional centre — Івано-Франківськ, 57 km: snow 1,410 Pa, wind 500 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
July: 118 kWh/kWp, December: 48 — 2.5 times less.
December: 48 against 38 in the oblast, 26.3% more.
| kWp | A year | July | December |
|---|---|---|---|
| 5 | 5,317 | 590 | 240 |
| 10 | 10,633 | 1,180 | 480 |
| 15 | 15,950 | 1,770 | 720 |
Snow and wind: Івано-Франківськ
Example: a 10 kW ground frame
For the loads of Ivano-Frankivsk: 11.16 kWp, 18 panels, 410 kg of steel, 16 piles, materials ≈ 54,212 UAH.
How these numbers are computed
Nearby
- Yaremche6 km1,040 kWh/kWp
- Tatariv8 km965 kWh/kWp
- Liuchky10 km1,070 kWh/kWp
- Bili Oslavy10 km1,087 kWh/kWp
- Chorni Oslavy11 km1,086 kWh/kWp
- Bania-Bereziv12 km1,096 kWh/kWp
All places: Nadvirnianskyi RaionIvano-Frankivsk Oblast: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.