Solar plant: site data
Solar power plant in Salatruk, Nadvirnianskyi Raion, Ivano-Frankivsk Oblast
Salatruk: 1,032 kWh per kWp a year, tilt 39° 9° east of south (PVGIS). 5.9% below the oblast median (1,097). #41 of 58 in the rayon, #649 of 700 in the oblast.
Nadvirna, the rayon centre, is 32 km away. 865 m above sea level — above 500 m the DBN snow and wind are higher. 32 km away: Nadvirna, the nearest bigger centre, 1,085 — 4.9% less here. Snow and wind from the nearest regional centre in the DBN — Івано-Франківськ, 62 km. 11.29 m between rows, pitch 15.01 m (latitude 48.5°).
- Yield of 1 kWp
- 1,032kWh/year
- Tilt
- 39°9° east of south
- 10 kW
- 10,322kWh/year
- Row pitch
- 15.01m · GCR 0.32
- T_min
- -38 °Cregion IIIA, Carpathian
- Snow S₀ / wind W₀
- 1,410 / 500Pa
Ground frame designer
A ground frame for a solar plant: Salatruk
The designer opens with this place’s coordinates, latitude 48.5° for the row spacing and the DBN loads of the nearest regional centre — Івано-Франківськ, 62 km: snow 1,410 Pa, wind 500 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
August: 119 kWh/kWp, December: 41 — 2.9 times less.
November: 56 against 48 in the oblast, 16.7% more.
| kWp | A year | August | December |
|---|---|---|---|
| 5 | 5,161 | 595 | 205 |
| 10 | 10,322 | 1,190 | 410 |
| 15 | 15,483 | 1,785 | 615 |
Snow and wind: Івано-Франківськ
Example: a 10 kW ground frame
For the loads of Ivano-Frankivsk: 11.16 kWp, 18 panels, 410 kg of steel, 16 piles, materials ≈ 54,212 UAH.
How these numbers are computed
Nearby
- Kupene2 km1,001 kWh/kWp
- Prychil2 km988 kWh/kWp
- Bystrytsia2 km975 kWh/kWp
- Tersovane2 km999 kWh/kWp
- Zghary3 km1,027 kWh/kWp
- Klympushi4 km1,011 kWh/kWp
All places: Nadvirnianskyi RaionIvano-Frankivsk Oblast: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.