Spain: solar plant site data

Solar power plant in Santa Cruz de Tenerife, Spain: yield, tilt angle and row spacing

Santa Cruz de Tenerife: 1,757 kWh per kWp a year at the optimal tilt of 26°, facing south (PVGIS). 8.8% above the median of the main cities of Spain (1,615). #6 of 147 main cities of Spain by yield. For comparison, Kyiv: 1,114 kWh/kWp — 57.7% more here.

Santa Cruz de Tenerife is in the province of Santa Cruz de Tenerife, Canary Islands. Population 211,359 (GeoNames). 10 m above sea level. 92 km away: Las Palmas de Gran Canaria, the nearest bigger city, 1,611 kWh/kWp — 9.1% more here. 3.01 m between rows, pitch 7.31 m, GCR 0.65 (latitude 28.5°).

Yield of 1 kWp
1,757kWh/year
Tilt
26°facing south
10 kW
17,571kWh/year
Row pitch
7.31m · GCR 0.65
Rank in the country
6of 147 cities

Ground frame designer

A ground frame for a solar plant: Santa Cruz de Tenerife

Latitude 28.5°: the tilt and the row pitch follow it. Enter the snow and wind for Spain in the designer, by the national annex to the Eurocode.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

120Jan123Feb153Mar159Apr166May161Jun173Jul171Aug156Sep143Oct117Nov115Dec

July: 173 kWh/kWp, December: 115 — 1.5 times less.

November: 117 against the median of 103 for the main cities of Spain, 13.6% more.

Santa Cruz de Tenerife: plants, kWh
kWpA yearJulyDecember
58,786865575
1017,5711,7301,150
1526,3572,5951,725

Fixed tilt facing south

What a table yields at another tilt than the optimal 26° — for roofs and frames with a standard slope.

Santa Cruz de Tenerife: yield at a fixed tilt, kWh/kWp
TiltA yearAgainst the optimum
26° (optimum)1,757—
15°1,735−1.3%
30°1,754−0.2%
45°1,680−4.4%
90°933−46.9%

Snow and wind loads

Snow and wind loads for a site in Spain follow CTE DB SE-AE (Spain’s Código Técnico de la Edificación) and, where the Eurocodes are applied, UNE-EN 1991-1-3 and UNE-EN 1991-1-4 with the Spanish National Annex. Solispec computes loads by the Ukrainian DBN V.1.2-2 only, so this page shows no snow or wind values for Spain: enter the characteristic values from these documents in the designer’s «Own snow S0» and «Own wind W0» fields.

The frame calculation for such a site is preliminary: before installation it must be checked by an engineer who works to the country’s standards.

Nearby cities

Spain: all cities and regions

Sources

Preliminary calculation: a design needs an engineer’s check.