Spain: solar plant site data

Solar power plant in Las Palmas de Gran Canaria, Spain: yield, tilt angle and row spacing

Las Palmas de Gran Canaria: 1,611 kWh per kWp a year at the optimal tilt of 27°, 9° west of south (PVGIS). Exactly the median of the main cities of Spain (1,615). #79 of 147 main cities of Spain by yield. For comparison, Kyiv: 1,114 kWh/kWp — 44.6% more here.

Las Palmas de Gran Canaria is in the province of Las Palmas, Canary Islands. Population 383,516 (GeoNames). 122 m above sea level. 1,357 km away: Seville, the nearest bigger city, 1,672 kWh/kWp — 3.6% less here. 3.07 m between rows, pitch 7.33 m, GCR 0.65 (latitude 28.1°).

Yield of 1 kWp
1,611kWh/year
Tilt
27°9° west of south
10 kW
16,107kWh/year
Row pitch
7.33m · GCR 0.65
Rank in the country
79of 147 cities

Ground frame designer

A ground frame for a solar plant: Las Palmas de Gran Canaria

Latitude 28.1°: the tilt and the row pitch follow it. Enter the snow and wind for Spain in the designer, by the national annex to the Eurocode.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

118Jan116Feb144Mar146Apr149May139Jun139Jul146Aug144Sep137Oct116Nov116Dec

May: 149 kWh/kWp, February: 116 — 1.3 times less.

July: 139 against the median of 166 for the main cities of Spain, 16.3% less.

Las Palmas de Gran Canaria: plants, kWh
kWpA yearMayFebruary
58,054745580
1016,1071,4901,160
1524,1612,2351,740

Fixed tilt facing south

What a table yields at another tilt than the optimal 27° — for roofs and frames with a standard slope.

Las Palmas de Gran Canaria: yield at a fixed tilt, kWh/kWp
TiltA yearAgainst the optimum
27° (optimum)1,611—
15°1,582−1.8%
30°1,606−0.3%
45°1,549−3.8%
90°908−43.6%

Snow and wind loads

Snow and wind loads for a site in Spain follow CTE DB SE-AE (Spain’s Código Técnico de la Edificación) and, where the Eurocodes are applied, UNE-EN 1991-1-3 and UNE-EN 1991-1-4 with the Spanish National Annex. Solispec computes loads by the Ukrainian DBN V.1.2-2 only, so this page shows no snow or wind values for Spain: enter the characteristic values from these documents in the designer’s «Own snow S0» and «Own wind W0» fields.

The frame calculation for such a site is preliminary: before installation it must be checked by an engineer who works to the country’s standards.

Nearby cities

Spain: all cities and regions

Sources

Preliminary calculation: a design needs an engineer’s check.