Spain: solar plant site data
Solar power plant in Roquetas de Mar, Spain: yield, tilt angle and row spacing
Roquetas de Mar: 1,779 kWh per kWp a year at the optimal tilt of 35°, 4° west of south (PVGIS). 10.1% above the median of the main cities of Spain (1,615). #3 of 147 main cities of Spain by yield. For comparison, Kyiv: 1,114 kWh/kWp — 59.7% more here.
Roquetas de Mar is in the province of Almería, Andalusia. Population 94,925 (GeoNames). 12 m above sea level. 16 km away: Almería, the nearest bigger city, 1,723 kWh/kWp — 3.3% more here. 5.47 m between rows, pitch 9.39 m, GCR 0.51 (latitude 36.8°).
- Yield of 1 kWp
- 1,779kWh/year
- Tilt
- 35°4° west of south
- 10 kW
- 17,789kWh/year
- Row pitch
- 9.39m · GCR 0.51
- Rank in the country
- 3of 147 cities
Ground frame designer
A ground frame for a solar plant: Roquetas de Mar
Latitude 36.8°: the tilt and the row pitch follow it. Enter the snow and wind for Spain in the designer, by the national annex to the Eurocode.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
July: 173 kWh/kWp, November: 120 — 1.4 times less.
November: 120 against the median of 103 for the main cities of Spain, 16.5% more.
| kWp | A year | July | November |
|---|---|---|---|
| 5 | 8,895 | 865 | 600 |
| 10 | 17,789 | 1,730 | 1,200 |
| 15 | 26,684 | 2,595 | 1,800 |
Snow and wind loads
Snow and wind loads for a site in Spain follow CTE DB SE-AE (Spain’s Código Técnico de la Edificación) and, where the Eurocodes are applied, UNE-EN 1991-1-3 and UNE-EN 1991-1-4 with the Spanish National Annex. Solispec computes loads by the Ukrainian DBN V.1.2-2 only, so this page shows no snow or wind values for Spain: enter the characteristic values from these documents in the designer’s «Own snow S0» and «Own wind W0» fields.
The frame calculation for such a site is preliminary: before installation it must be checked by an engineer who works to the country’s standards.
Nearby cities
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation, population and divisions (changed)
- Where to take snow and wind loads from: CTE DB SE-AE
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.