Spain: solar plant site data

Solar power plant in Granada, Spain: yield, tilt angle and row spacing

Granada: 1,673 kWh per kWp a year at the optimal tilt of 35°, 4° east of south (PVGIS). 3.6% above the median of the main cities of Spain (1,615). #27 of 147 main cities of Spain by yield. For comparison, Kyiv: 1,114 kWh/kWp — 50.2% more here.

Granada is in the province of Granada, Andalusia. Population 233,532 (GeoNames). 689 m above sea level. 89 km away: Málaga, the nearest bigger city, 1,698 kWh/kWp — 1.5% less here. 5.58 m between rows, pitch 9.50 m, GCR 0.50 (latitude 37.2°).

Yield of 1 kWp
1,673kWh/year
Tilt
35°4° east of south
10 kW
16,733kWh/year
Row pitch
9.50m · GCR 0.50
Rank in the country
27of 147 cities

Ground frame designer

A ground frame for a solar plant: Granada

Latitude 37.2°: the tilt and the row pitch follow it. Enter the snow and wind for Spain in the designer, by the national annex to the Eurocode.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

121Jan117Feb141Mar141Apr155May157Jun166Jul164Aug147Sep135Oct113Nov117Dec

July: 166 kWh/kWp, November: 113 — 1.5 times less.

December: 117 against the median of 103 for the main cities of Spain, 13.6% more.

Granada: plants, kWh
kWpA yearJulyNovember
58,367830565
1016,7331,6601,130
1525,1002,4901,695

Fixed tilt facing south

What a table yields at another tilt than the optimal 35° — for roofs and frames with a standard slope.

Granada: yield at a fixed tilt, kWh/kWp
TiltA yearAgainst the optimum
35° (optimum)1,673—
15°1,596−4.6%
30°1,668−0.3%
45°1,653−1.2%
90°1,070−36.1%

Snow and wind loads

Snow and wind loads for a site in Spain follow CTE DB SE-AE (Spain’s Código Técnico de la Edificación) and, where the Eurocodes are applied, UNE-EN 1991-1-3 and UNE-EN 1991-1-4 with the Spanish National Annex. Solispec computes loads by the Ukrainian DBN V.1.2-2 only, so this page shows no snow or wind values for Spain: enter the characteristic values from these documents in the designer’s «Own snow S0» and «Own wind W0» fields.

The frame calculation for such a site is preliminary: before installation it must be checked by an engineer who works to the country’s standards.