Spain: solar plant site data

Solar power plant in Jaén, Spain: yield, tilt angle and row spacing

Jaén: 1,648 kWh per kWp a year at the optimal tilt of 34°, 11° east of south (PVGIS). 2.0% above the median of the main cities of Spain (1,615). #36 of 147 main cities of Spain by yield. For comparison, Kyiv: 1,114 kWh/kWp — 48.0% more here.

Jaén is in the province of Jaén, Andalusia. Population 113,457 (GeoNames). 558 m above sea level. 67 km away: Granada, the nearest bigger city, 1,673 kWh/kWp — 1.5% less here. 5.58 m between rows, pitch 9.55 m, GCR 0.50 (latitude 37.8°).

Yield of 1 kWp
1,648kWh/year
Tilt
34°11° east of south
10 kW
16,482kWh/year
Row pitch
9.55m · GCR 0.50
Rank in the country
36of 147 cities

Ground frame designer

A ground frame for a solar plant: Jaén

Latitude 37.8°: the tilt and the row pitch follow it. Enter the snow and wind for Spain in the designer, by the national annex to the Eurocode.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

110Jan113Feb140Mar143Apr157May158Jun168Jul166Aug146Sep132Oct107Nov108Dec

July: 168 kWh/kWp, November: 107 — 1.6 times less.

December: 108 against the median of 103 for the main cities of Spain, 4.9% more.

Jaén: plants, kWh
kWpA yearJulyNovember
58,241840535
1016,4821,6801,070
1524,7232,5201,605

Fixed tilt facing south

What a table yields at another tilt than the optimal 34° — for roofs and frames with a standard slope.

Jaén: yield at a fixed tilt, kWh/kWp
TiltA yearAgainst the optimum
34° (optimum)1,648—
15°1,574−4.5%
30°1,639−0.5%
45°1,620−1.7%
90°1,039−36.9%

Snow and wind loads

Snow and wind loads for a site in Spain follow CTE DB SE-AE (Spain’s Código Técnico de la Edificación) and, where the Eurocodes are applied, UNE-EN 1991-1-3 and UNE-EN 1991-1-4 with the Spanish National Annex. Solispec computes loads by the Ukrainian DBN V.1.2-2 only, so this page shows no snow or wind values for Spain: enter the characteristic values from these documents in the designer’s «Own snow S0» and «Own wind W0» fields.

The frame calculation for such a site is preliminary: before installation it must be checked by an engineer who works to the country’s standards.

Nearby cities

Spain: all cities and regions

Sources

Preliminary calculation: a design needs an engineer’s check.