Solar plant: site data

Solar power plant in Mezhyrich, Cherkaskyi Raion, Cherkasy Oblast

Mezhyrich: 1,141 kWh per kWp a year, tilt 38° 4° east of south (PVGIS). Exactly the oblast median (1,144). #168 of 207 in the rayon, #460 of 731 in the oblast.

Cherkasy, the rayon centre, is 49 km away. 79 m above sea level. 15 km away: Kaniv, the nearest bigger centre, the same 1,143. Snow and wind from the nearest regional centre in the DBN — Черкаси, 49 km. 12.01 m between rows, pitch 15.78 m (latitude 49.6°).

Yield of 1 kWp
1,141kWh/year
Tilt
38°4° east of south
10 kW
11,411kWh/year
Row pitch
15.78m · GCR 0.30
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,520 / 420Pa

Ground frame designer

A ground frame for a solar plant: Mezhyrich

The designer opens with this place’s coordinates, latitude 49.6° for the row spacing and the DBN loads of the nearest regional centre — Черкаси, 49 km: snow 1,520 Pa, wind 420 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

41Jan59Feb98Mar116Apr136May139Jun143Jul141Aug114Sep85Oct38Nov31Dec

July: 143 kWh/kWp, December: 31 — 4.6 times less.

January: 41 against 35 in the oblast, 17.1% more.

Mezhyrich: plants, kWh
kWpA yearJulyDecember
55,706715155
1011,4111,430310
1517,1172,145465

Snow and wind: Черкаси

Example: a 10 kW ground frame

For the loads of Cherkasy: 11.16 kWp, 18 panels, 372 kg of steel, 12 piles, materials ≈ 49,705 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Cherkaskyi RaionCherkasy Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.