Solar plant: site data
Solar power plant in Horobiivka, Cherkaskyi Raion, Cherkasy Oblast
Horobiivka: 1,145 kWh per kWp a year, tilt 38° 3° east of south (PVGIS). Exactly the oblast median (1,144). #131 of 207 in the rayon, #338 of 731 in the oblast.
Cherkasy, the rayon centre, is 49 km away. 168 m above sea level. 20 km away: Kaniv, the nearest bigger centre, the same 1,143. Snow and wind from the nearest regional centre in the DBN — Черкаси, 50 km. 11.97 m between rows, pitch 15.74 m (latitude 49.6°).
- Yield of 1 kWp
- 1,145kWh/year
- Tilt
- 38°3° east of south
- 10 kW
- 11,448kWh/year
- Row pitch
- 15.74m · GCR 0.30
- T_min
- -40 °Cregion I, north-western
- Snow S₀ / wind W₀
- 1,520 / 420Pa
Ground frame designer
A ground frame for a solar plant: Horobiivka
The designer opens with this place’s coordinates, latitude 49.6° for the row spacing and the DBN loads of the nearest regional centre — Черкаси, 50 km: snow 1,520 Pa, wind 420 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
July: 143 kWh/kWp, December: 31 — 4.6 times less.
January: 40 against 35 in the oblast, 14.3% more.
| kWp | A year | July | December |
|---|---|---|---|
| 5 | 5,724 | 715 | 155 |
| 10 | 11,448 | 1,430 | 310 |
| 15 | 17,172 | 2,145 | 465 |
Example: a 10 kW ground frame
For the loads of Cherkasy: 11.16 kWp, 18 panels, 372 kg of steel, 12 piles, materials ≈ 49,705 UAH.
How these numbers are computed
Nearby
- Buda-Horobiivska3 km1,143 kWh/kWp
- Luka3 km1,139 kWh/kWp
- Popivka5 km1,141 kWh/kWp
- Mezhyrich5 km1,141 kWh/kWp
- Sakhnivka7 km1,144 kWh/kWp
- Babychi7 km1,137 kWh/kWp
All places: Cherkaskyi RaionCherkasy Oblast: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.