Solar plant: site data

Solar power plant in Ksaverove, Cherkaskyi Raion, Cherkasy Oblast

Ksaverove: 1,145 kWh per kWp a year, tilt 36° 3° east of south (PVGIS). Exactly the oblast median (1,144). #126 of 207 in the rayon, #319 of 731 in the oblast.

Cherkasy, the rayon centre, is 48 km away. 158 m above sea level. 12 km away: Horodyshche, the nearest bigger centre, the same 1,145. Snow and wind from the nearest regional centre in the DBN — Черкаси, 48 km. 11.11 m between rows, pitch 14.98 m (latitude 49.2°).

Yield of 1 kWp
1,145kWh/year
Tilt
36°3° east of south
10 kW
11,453kWh/year
Row pitch
14.98m · GCR 0.32
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,520 / 420Pa

Ground frame designer

A ground frame for a solar plant: Ksaverove

The designer opens with this place’s coordinates, latitude 49.2° for the row spacing and the DBN loads of the nearest regional centre — Черкаси, 48 km: snow 1,520 Pa, wind 420 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

35Jan57Feb97Mar119Apr138May142Jun148Jul143Aug117Sep87Oct38Nov24Dec

July: 148 kWh/kWp, December: 24 — 6.2 times less.

December: 24 against 28 in the oblast, 14.3% less.

Ksaverove: plants, kWh
kWpA yearJulyDecember
55,727740120
1011,4531,480240
1517,1802,220360

Snow and wind: Черкаси

Example: a 10 kW ground frame

For the loads of Cherkasy: 11.16 kWp, 18 panels, 372 kg of steel, 12 piles, materials ≈ 49,705 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Cherkaskyi RaionCherkasy Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.