Section of the table from the Solispec engine (median zone — Cherkasy)

SunPower/Maxeon

Ground frame for 24 Maxeon 3 SPR-MAX3-430-R (IBC) panels (2×12)

2 rows of 12 panels, 10.32 kW. The Solispec engine chose the profiles, the frame pitch and the footings for three snow and wind zones: Kherson has the lowest load of the regional centres, Cherkasy the median, Chernihiv the highest.

Power
10.32kW
Steel
352.4kg
Posts
12
Bolts
154
Materials
47,422₴
Yield
11,752kWh/year

Figures for the median zone (Cherkasy); all three zones are in the table below.

Ground frame designer

Open this frame in the builder

The builder opens with the Maxeon 3 SPR-MAX3-430-R (IBC) panel and the 2 × 12 layout; site — Cherkasy. Change the site, the tilt or the profiles and the checks and estimate are recalculated.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Three snow and wind zones

The same table designed for three regional centres: with the lowest, the median and the highest combined snow and wind load under DBN V.1.2-2:2006. For another site, open the frame in the builder.

ParameterLow loadKherson · S₀ 760 · W₀ 480Median loadCherkasy · S₀ 1,520 · W₀ 420High loadChernihiv · S₀ 1,720 · W₀ 410
PostsTube 60×60×2Tube 60×60×2Tube 60×60×2
RaftersC-channel 60×40×2C-channel 60×40×2C-channel 60×40×2
Purlins and bracesC-channel 60×40×2C-channel 60×40×2C-channel 60×40×2
Frames6 frames, pitch up to 2,440 mm6 frames, pitch up to 2,440 mm7 frames, pitch up to 2,050 mm
Posts121214
Footings (bored concrete)12 pcs, Ø400 mm, depth 1,100 mm12 pcs, Ø300 mm, depth 1,300 mm14 pcs, Ø300 mm, depth 1,300 mm
Concrete1.83 m³1.21 m³1.42 m³
Tilt30°30°30°
Panel bottom / post top600 / 1,874 mm600 / 1,874 mm600 / 1,874 mm
Panel field size12,912 × 2,387 mm12,912 × 2,387 mm12,912 × 2,387 mm
Row spacing between tables (no shade on 21 December)8,180 mm at noon · 9,190 mm ±2 h9,060 mm at noon · 10,470 mm ±2 h9,930 mm at noon · 11,800 mm ±2 h
Steel343.7 kg352.4 kg380.3 kg
BoltsM10 — 102, M8 — 52M10 — 102, M8 — 52M10 — 112, M8 — 52
Panel clampsend 8, middle 44end 8, middle 44end 8, middle 44
Materials49,551 UAH47,422 UAH50,356 UAH
With installation and delivery76,511 UAH74,382 UAH77,266 UAH
Per 1 kW7,414 UAH/kW7,208 UAH/kW7,487 UAH/kW
Yield1,266 kWh/kW · 13,070 kWh/year1,139 kWh/kW · 11,752 kWh/year1,043 kWh/kW · 10,765 kWh/year
Strength σ/fy72%100%76%
Deflection / (L/200)70%95%61%
Rafter strength67%92%83%
Post utilisation14%19%17%
Utilisation86%90%74%
Depth vs frost depthokokok
Checks overallwith a cautionwith a cautionwith a caution

Checks and cautions

Member utilisation as the engine computes it. Cautions are checks that pass, but with a small margin.

  • Embedment, mmThe footing resists wind uplift at above 80 % utilisation, or it is shallower than the frost depth. The soil resistance in the calculation is an estimate — check the soil on site.Kherson: Foundation Ø400 × 1 100: 0.138 m³ of concrete per post. Wind uplift on the front post ≈ 11.5 kN (with γ=1.5) vs ≈ 13.4 kN (concrete weight + soil friction, estimate) → 86%.Cherkasy: Foundation Ø300 × 1 300: 0.092 m³ of concrete per post. Wind uplift on the front post ≈ 10.0 kN (with γ=1.5) vs ≈ 11.2 kN (concrete weight + soil friction, estimate) → 90%.
  • Max. frame pitch, mmThe purlins between the frames are used above 80 % (strength or deflection): the structure passes, but the margin is small. A shorter frame pitch or a deeper purlin gives more margin.Cherkasy: Frame spacing 2 440 mm, 6 frames. Purlin C-channel 60×40×2: strength 100%, deflection 95% of L/200 (snow on panel 977 Pa).
  • Rafter profileThe rafter is used above 80 %, or the frame's posts stand far apart: the structure passes, but the margin is small.Cherkasy: Rafter C-channel 60×40×2: span between posts 1 766, cantilever 639 mm → strength 92%.Chernihiv: Rafter C-channel 60×40×2: span between posts 1 766, cantilever 639 mm → strength 83%.

Bill of materials

The parts of one table for the median zone (Cherkasy): mark, name, profile, cut length, quantity.

MarkPartProfileLength, mmQuantity
П1Front postTube 60×60×22,3176
П2Rear postTube 60×60×23,1996
Кр1Rafter (inclined beam)C-channel 60×40×23,0446
Пк1Frame strutC-channel 60×40×21,4596
Х1Longitudinal brace (cross)C-channel 60×40×22,7584
Р1Purlin (rail)C-channel 60×40×26,0002
Р2Purlin (rail)C-channel 60×40×26,0002
Р3Purlin (rail)C-channel 60×40×26,0002
Р4Purlin (rail)C-channel 60×40×26,0002
Р5Purlin (rail)C-channel 60×40×29122
Р6Purlin (rail)C-channel 60×40×29122
—Bolt M10×25 set · purlins, braces, connectors——34
—Bolt M10×80 set · purlin to rafter——24
—Bolt M10×90 set · strut to post — through spacer inserts——6
—Bolt M10×130 set · post–rafter — through spacer inserts——24
—Bolt M10×140 set · strut to rafter — through spacer inserts——6
—Bolt M10×150 set · brace to post — through spacer inserts——8
—End clamp 40 mm——8
—Mid clamp (30–40 mm)——44
—Bolt M8×60 + channel nut——52
—Concrete for 12 posts, Ø300×1300——1.21 m³

Profile cutting

22 bars of 6,000 mm, 122.8 m of profile in total.

  • Tube 60×60×26 bars
  • C-channel 60×40×216 bars

Estimated cost

The engine's materials estimate for the median zone (Cherkasy).

Materials
47,422₴
With installation and delivery
74,382₴
Per 1 kW
7,208UAH/kW

The engine's estimate has 23 lines; the full list is in the builder. Prices are the typical market prices built into the Solispec engine, as of 06.10.2026; no margin, no VAT.

Yield

Yield: 1,139 kWh per 1 kW a year, ≈ 11,752 kWh a year in total (median zone, Cherkasy; tilt 30°, the optimum for the latitude is 35.3°).

A preliminary calculation; a design needs an engineer's check. Snow and wind per DBN V.1.2-2:2006 for the regional centre; profiles, footings and estimate by the Solispec engine 0.12.0.