Section of the table from the Solispec engine (median zone — Cherkasy)

Jinko

Ground frame for 20 Jinko Tiger Neo JKM485N-60HL4-V panels (2×10)

2 rows of 10 panels, 9.70 kW. The Solispec engine chose the profiles, the frame pitch and the footings for three snow and wind zones: Kherson has the lowest load of the regional centres, Cherkasy the median, Chernihiv the highest.

Power
9.70kW
Steel
342.7kg
Posts
12
Bolts
130
Materials
46,154₴
Yield
11,046kWh/year

Figures for the median zone (Cherkasy); all three zones are in the table below.

Ground frame designer

Open this frame in the builder

The builder opens with the Jinko Tiger Neo JKM485N-60HL4-V panel and the 2 × 10 layout; site — Cherkasy. Change the site, the tilt or the profiles and the checks and estimate are recalculated.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Three snow and wind zones

The same table designed for three regional centres: with the lowest, the median and the highest combined snow and wind load under DBN V.1.2-2:2006. For another site, open the frame in the builder.

ParameterLow loadKherson · S₀ 760 · W₀ 480Median loadCherkasy · S₀ 1,520 · W₀ 420High loadChernihiv · S₀ 1,720 · W₀ 410
PostsTube 60×60×2Tube 60×60×2Tube 60×60×2
RaftersC-channel 60×40×2C-channel 60×40×2C-channel 60×40×2
Purlins and bracesC-channel 60×40×2C-channel 60×40×2C-channel 60×40×2
Frames6 frames, pitch up to 2,200 mm6 frames, pitch up to 2,200 mm6 frames, pitch up to 2,200 mm
Posts121212
Footings (bored concrete)12 pcs, Ø350 mm, depth 1,100 mm12 pcs, Ø300 mm, depth 1,300 mm12 pcs, Ø300 mm, depth 1,300 mm
Concrete1.40 m³1.21 m³1.21 m³
Tilt30°30°30°
Panel bottom / post top600 / 1,943 mm600 / 1,943 mm600 / 1,943 mm
Panel field size11,660 × 2,506 mm11,660 × 2,506 mm11,660 × 2,506 mm
Row spacing between tables (no shade on 21 December)8,600 mm at noon · 9,670 mm ±2 h9,530 mm at noon · 11,010 mm ±2 h10,440 mm at noon · 12,410 mm ±2 h
Steel334.1 kg342.7 kg342.7 kg
BoltsM10 — 86, M8 — 44M10 — 86, M8 — 44M10 — 86, M8 — 44
Panel clampsend 8, middle 36end 8, middle 36end 8, middle 36
Materials46,660 UAH46,154 UAH46,154 UAH
With installation and delivery72,047 UAH71,541 UAH71,541 UAH
Per 1 kW7,428 UAH/kW7,375 UAH/kW7,375 UAH/kW
Yield1,266 kWh/kW · 12,284 kWh/year1,139 kWh/kW · 11,046 kWh/year1,043 kWh/kW · 10,118 kWh/year
Strength σ/fy62%86%92%
Deflection / (L/200)54%74%79%
Rafter strength67%92%99%
Post utilisation13%18%20%
Utilisation97%86%84%
Depth vs frost depthokokok
Checks overallwith a cautionwith a cautionwith a caution

Checks and cautions

Member utilisation as the engine computes it. Cautions are checks that pass, but with a small margin.

  • Embedment, mmThe footing resists wind uplift at above 80 % utilisation, or it is shallower than the frost depth. The soil resistance in the calculation is an estimate — check the soil on site.Kherson: Foundation Ø350 × 1 100: 0.106 m³ of concrete per post. Wind uplift on the front post ≈ 11.0 kN (with γ=1.5) vs ≈ 11.4 kN (concrete weight + soil friction, estimate) → 97%.Cherkasy: Foundation Ø300 × 1 300: 0.092 m³ of concrete per post. Wind uplift on the front post ≈ 9.6 kN (with γ=1.5) vs ≈ 11.2 kN (concrete weight + soil friction, estimate) → 86%.Chernihiv: Foundation Ø300 × 1 300: 0.092 m³ of concrete per post. Wind uplift on the front post ≈ 9.4 kN (with γ=1.5) vs ≈ 11.2 kN (concrete weight + soil friction, estimate) → 84%.
  • Max. frame pitch, mmThe purlins between the frames are used above 80 % (strength or deflection): the structure passes, but the margin is small. A shorter frame pitch or a deeper purlin gives more margin.Cherkasy: Frame spacing 2 200 mm, 6 frames. Purlin C-channel 60×40×2: strength 86%, deflection 74% of L/200 (snow on panel 977 Pa).Chernihiv: Frame spacing 2 200 mm, 6 frames. Purlin C-channel 60×40×2: strength 92%, deflection 79% of L/200 (snow on panel 1 106 Pa).
  • Rafter profileThe rafter is used above 80 %, or the frame's posts stand far apart: the structure passes, but the margin is small.Cherkasy: Rafter C-channel 60×40×2: span between posts 1 851, cantilever 670 mm → strength 92%.Chernihiv: Rafter C-channel 60×40×2: span between posts 1 851, cantilever 670 mm → strength 99%.

Bill of materials

The parts of one table for the median zone (Cherkasy): mark, name, profile, cut length, quantity.

MarkPartProfileLength, mmQuantity
П1Front postTube 60×60×22,3426
П2Rear postTube 60×60×23,2686
Кр1Rafter (inclined beam)C-channel 60×40×23,1926
Пк1Frame strutC-channel 60×40×21,5186
Х1Longitudinal brace (cross)C-channel 60×40×22,5774
Р1Purlin (rail)C-channel 60×40×26,0002
Р2Purlin (rail)C-channel 60×40×26,0002
Р3Purlin (rail)C-channel 60×40×25,6602
Р4Purlin (rail)C-channel 60×40×25,6602
—Bolt M10×25 set · purlins, braces, connectors——18
—Bolt M10×80 set · purlin to rafter——24
—Bolt M10×90 set · strut to post — through spacer inserts——6
—Bolt M10×130 set · post–rafter — through spacer inserts——24
—Bolt M10×140 set · strut to rafter — through spacer inserts——6
—Bolt M10×150 set · brace to post — through spacer inserts——8
—End clamp 30 mm——8
—Mid clamp (30–40 mm)——36
—Bolt M8×50 + channel nut——44
—Concrete for 12 posts, Ø300×1300——1.21 m³

Profile cutting

22 bars of 6,000 mm, 118.9 m of profile in total.

  • Tube 60×60×26 bars
  • C-channel 60×40×216 bars

Estimated cost

The engine's materials estimate for the median zone (Cherkasy).

Materials
46,154₴
With installation and delivery
71,541₴
Per 1 kW
7,375UAH/kW

The engine's estimate has 23 lines; the full list is in the builder. Prices are the typical market prices built into the Solispec engine, as of 06.10.2026; no margin, no VAT.

Yield

Yield: 1,139 kWh per 1 kW a year, ≈ 11,046 kWh a year in total (median zone, Cherkasy; tilt 30°, the optimum for the latitude is 35.3°).

A preliminary calculation; a design needs an engineer's check. Snow and wind per DBN V.1.2-2:2006 for the regional centre; profiles, footings and estimate by the Solispec engine 0.12.0.