Solar plant: site data
Solar power plant in Kvasy, Rakhivskyi Raion, Zakarpattia Oblast
Kvasy: 1,059 kWh per kWp a year, tilt 36° 7° east of south (PVGIS). 7.2% below the oblast median (1,141). #22 of 36 in the rayon, #514 of 613 in the oblast.
Rakhiv, the rayon centre, is 13 km away. 546 m above sea level — above 500 m the DBN snow and wind are higher. 13 km away: Rakhiv, the nearest bigger centre, 1,068 — 0.9% less here. Snow and wind from the nearest regional centre in the DBN — Івано-Франківськ, 91 km. 10.32 m between rows, pitch 14.19 m (latitude 48.2°).
- Yield of 1 kWp
- 1,059kWh/year
- Tilt
- 36°7° east of south
- 10 kW
- 10,586kWh/year
- Row pitch
- 14.19m · GCR 0.34
- T_min
- -38 °Cregion IIIA, Carpathian
- Snow S₀ / wind W₀
- 1,410 / 500Pa
Ground frame designer
A ground frame for a solar plant: Kvasy
The designer opens with this place’s coordinates, latitude 48.2° for the row spacing and the DBN loads of the nearest regional centre — Івано-Франківськ, 91 km: snow 1,410 Pa, wind 500 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
August: 132 kWh/kWp, December: 33 — 4.0 times less.
January: 45 against 39 in the oblast, 15.4% more.
| kWp | A year | August | December |
|---|---|---|---|
| 5 | 5,293 | 660 | 165 |
| 10 | 10,586 | 1,320 | 330 |
| 15 | 15,879 | 1,980 | 495 |
Snow and wind: Івано-Франківськ
Example: a 10 kW ground frame
For the loads of Ivano-Frankivsk: 11.16 kWp, 18 panels, 410 kg of steel, 16 piles, materials ≈ 54,212 UAH.
How these numbers are computed
Nearby
- Trostianets2 km1,074 kWh/kWp
- Sitnyi4 km1,040 kWh/kWp
- Bilyn5 km1,048 kWh/kWp
- Surdok5 km971 kWh/kWp
- Kevelovo9 km1,033 kWh/kWp
- Kleva10 km1,020 kWh/kWp
All places: Rakhivskyi RaionZakarpattia Oblast: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.