Solar plant: site data

Solar power plant in Shmidtove, Mykolaivskyi Raion, Mykolaiv Oblast

Shmidtove: 1,244 kWh per kWp a year, tilt 36° 3° east of south (PVGIS). 3.9% above the oblast median (1,198). #109 of 238 in the rayon, #112 of 909 in the oblast.

Mykolayiv, the rayon centre, is 38 km away. 39 m above sea level. 28 km away: Bilozerka, the nearest bigger centre, 1,286 — 3.3% less here. Snow and wind from the nearest regional centre in the DBN — Херсон, 29 km. 9.48 m between rows, pitch 13.35 m (latitude 46.9°).

Yield of 1 kWp
1,244kWh/year
Tilt
36°3° east of south
10 kW
12,441kWh/year
Row pitch
13.35m · GCR 0.36
T_min
-42 °Cregion II, south-eastern
Snow S₀ / wind W₀
760 / 480Pa

Ground frame designer

A ground frame for a solar plant: Shmidtove

The designer opens with this place’s coordinates, latitude 46.9° for the row spacing and the DBN loads of the nearest regional centre — Херсон, 29 km: snow 760 Pa, wind 480 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

42Jan61Feb107Mar129Apr142May142Jun152Jul152Aug129Sep99Oct54Nov38Dec

July: 152 kWh/kWp, December: 38 — 4.0 times less.

December: 38 against 33 in the oblast, 15.2% more.

Shmidtove: plants, kWh
kWpA yearJulyDecember
56,221760190
1012,4411,520380
1518,6622,280570

Snow and wind: Херсон

Example: a 10 kW ground frame

For the loads of Kherson: 11.16 kWp, 18 panels, 349 kg of steel, 12 piles, materials ≈ 47,980 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Mykolaivskyi RaionMykolaiv Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.