Solar plant: site data

Solar power plant in Novoandriyivka, Mykolaivskyi Raion, Mykolaiv Oblast

Novoandriyivka: 1,220 kWh per kWp a year, tilt 37° 3° east of south (PVGIS). 1.9% above the oblast median (1,198). #201 of 238 in the rayon, #267 of 909 in the oblast.

Mykolayiv, the rayon centre, is 46 km away. 17 m above sea level. 11 km away: Nova Odesa, the nearest bigger centre, 1,212 — 0.7% more here. Snow and wind from the nearest regional centre in the DBN — Миколаїв, 47 km. 9.99 m between rows, pitch 13.81 m (latitude 47.3°).

Yield of 1 kWp
1,220kWh/year
Tilt
37°3° east of south
10 kW
12,204kWh/year
Row pitch
13.81m · GCR 0.35
T_min
-42 °Cregion II, south-eastern
Snow S₀ / wind W₀
870 / 470Pa

Ground frame designer

A ground frame for a solar plant: Novoandriyivka

The designer opens with this place’s coordinates, latitude 47.3° for the row spacing and the DBN loads of the nearest regional centre — Миколаїв, 47 km: snow 870 Pa, wind 470 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

42Jan60Feb104Mar125Apr140May141Jun152Jul149Aug125Sep97Oct50Nov36Dec

July: 152 kWh/kWp, December: 36 — 4.2 times less.

February: 60 against 54 in the oblast, 11.1% more.

Novoandriyivka: plants, kWh
kWpA yearJulyDecember
56,102760180
1012,2041,520360
1518,3062,280540

Snow and wind: Миколаїв

Example: a 10 kW ground frame

For the loads of Mykolaiv: 11.16 kWp, 18 panels, 372 kg of steel, 14 piles, materials ≈ 50,842 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Mykolaivskyi RaionMykolaiv Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.