Solar plant: site data
Solar power plant in Ivashkivtsi, Sambirskyi Raion, Lviv Oblast
Ivashkivtsi: 1,035 kWh per kWp a year, tilt 36° facing south (PVGIS). 4.5% below the oblast median (1,084). #226 of 264 in the rayon, #1447 of 1532 in the oblast.
Sambir, the rayon centre, is 72 km away. 697 m above sea level — above 500 m the DBN snow and wind are higher. 50 km away: Perechyn, the nearest bigger centre, 1,100 — 5.9% less here. Snow and wind from the nearest regional centre in the DBN — Ужгород, 67 km. 10.85 m between rows, pitch 14.72 m (latitude 48.9°).
- Yield of 1 kWp
- 1,035kWh/year
- Tilt
- 36°facing south
- 10 kW
- 10,354kWh/year
- Row pitch
- 14.72m · GCR 0.33
- T_min
- -38 °Cregion IIIA, Carpathian
- Snow S₀ / wind W₀
- 1,340 / 370Pa
Ground frame designer
A ground frame for a solar plant: Ivashkivtsi
The designer opens with this place’s coordinates, latitude 48.9° for the row spacing and the DBN loads of the nearest regional centre — Ужгород, 67 km: snow 1,340 Pa, wind 370 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
July: 128 kWh/kWp, December: 27 — 4.7 times less.
December: 27 against 32 in the oblast, 15.6% less.
| kWp | A year | July | December |
|---|---|---|---|
| 5 | 5,177 | 640 | 135 |
| 10 | 10,354 | 1,280 | 270 |
| 15 | 15,531 | 1,920 | 405 |
Example: a 10 kW ground frame
For the loads of Uzhhorod: 11.16 kWp, 18 panels, 366 kg of steel, 12 piles, materials ≈ 48,597 UAH.
How these numbers are computed
Nearby
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.