Solar plant: site data

Solar power plant in Khreshchatyi Yar, Bilotserkivskyi Raion, Kyiv Oblast

Khreshchatyi Yar: 1,129 kWh per kWp a year, tilt 36° 3° east of south (PVGIS). 0.6% above the oblast median (1,122). #90 of 260 in the rayon, #323 of 1071 in the oblast.

Bila Tserkva, the rayon centre, is 34 km away. 205 m above sea level. 34 km away: Bila Tserkva, the nearest bigger centre, 1,122 — 0.6% more here. Snow and wind from the nearest regional centre in the DBN — Київ, 102 km. 11.40 m between rows, pitch 15.27 m (latitude 49.5°).

Yield of 1 kWp
1,129kWh/year
Tilt
36°3° east of south
10 kW
11,287kWh/year
Row pitch
15.27m · GCR 0.31
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,550 / 370Pa

Ground frame designer

A ground frame for a solar plant: Khreshchatyi Yar

The designer opens with this place’s coordinates, latitude 49.5° for the row spacing and the DBN loads of the nearest regional centre — Київ, 102 km: snow 1,550 Pa, wind 370 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

33Jan54Feb96Mar118Apr138May142Jun145Jul141Aug114Sep85Oct37Nov26Dec

July: 145 kWh/kWp, December: 26 — 5.6 times less.

December: 26 against 27 in the oblast, 3.7% less.

Khreshchatyi Yar: plants, kWh
kWpA yearJulyDecember
55,644725130
1011,2871,450260
1516,9312,175390

Snow and wind: Київ

Example: a 10 kW ground frame

For the loads of Kyiv: 11.16 kWp, 18 panels, 376 kg of steel, 12 piles, materials ≈ 47,122 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Bilotserkivskyi RaionKyiv Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.