Solar plant: site data

Solar power plant in Novosel’skoye, Yevpatoriiskyi Raion, Autonomous Republic of Crimea

Novosel’skoye: 1,332 kWh per kWp a year, tilt 36° facing south (PVGIS). 3.7% above the oblast median (1,284). #48 of 120 in the rayon, #109 of 1025 in the oblast.

Yevpatoriya, the rayon centre, is 60 km away. 15 m above sea level. 60 km away: Yevpatoriya, the nearest bigger centre, the same 1,338. Snow and wind from the nearest regional centre in the DBN — Херсон, 127 km. 8.71 m between rows, pitch 12.58 m (latitude 45.5°).

Yield of 1 kWp
1,332kWh/year
Tilt
36°facing south
10 kW
13,320kWh/year
Row pitch
12.58m · GCR 0.38
T_min
-27 °Cregion V, Crimean Mountains
Snow S₀ / wind W₀
760 / 480Pa

Ground frame designer

A ground frame for a solar plant: Novosel’skoye

The designer opens with this place’s coordinates, latitude 45.5° for the row spacing and the DBN loads of the nearest regional centre — Херсон, 127 km: snow 760 Pa, wind 480 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

48Jan65Feb114Mar138Apr154May150Jun163Jul159Aug135Sep102Oct62Nov44Dec

July: 163 kWh/kWp, December: 44 — 3.7 times less.

March: 114 against 106 in the oblast, 7.5% more.

Novosel’skoye: plants, kWh
kWpA yearJulyDecember
56,660815220
1013,3201,630440
1519,9802,445660

Snow and wind: Херсон

Example: a 10 kW ground frame

For the loads of Kherson: 11.16 kWp, 18 panels, 349 kg of steel, 12 piles, materials ≈ 47,980 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Yevpatoriiskyi RaionAutonomous Republic of Crimea: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.