Solar plant: site data

Solar power plant in Chornomorske, Kerchenskyi Raion, Autonomous Republic of Crimea

Chornomorske: 1,310 kWh per kWp a year, tilt 35° 4° west of south (PVGIS). 2.0% above the oblast median (1,284). #30 of 71 in the rayon, #274 of 1025 in the oblast.

Kerch, the rayon centre, is 53 km away. 16 m above sea level. 46 km away: Feodosiya, the nearest bigger centre, 1,277 — 2.5% more here. Snow and wind from the nearest regional centre in the DBN — Херсон, 315 km. 8.27 m between rows, pitch 12.19 m (latitude 45.0°).

Yield of 1 kWp
1,310kWh/year
Tilt
35°4° west of south
10 kW
13,095kWh/year
Row pitch
12.19m · GCR 0.39
T_min
-27 °Cregion V, Crimean Mountains
Snow S₀ / wind W₀
760 / 480Pa

Ground frame designer

A ground frame for a solar plant: Chornomorske

The designer opens with this place’s coordinates, latitude 45.0° for the row spacing and the DBN loads of the nearest regional centre — Херсон, 315 km: snow 760 Pa, wind 480 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

51Jan70Feb104Mar131Apr145May149Jun157Jul158Aug132Sep103Oct63Nov47Dec

August: 158 kWh/kWp, December: 47 — 3.4 times less.

February: 70 against 64 in the oblast, 9.4% more.

Chornomorske: plants, kWh
kWpA yearAugustDecember
56,548790235
1013,0951,580470
1519,6432,370705

Snow and wind: Херсон

Example: a 10 kW ground frame

For the loads of Kherson: 11.16 kWp, 18 panels, 349 kg of steel, 12 piles, materials ≈ 47,980 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Kerchenskyi RaionAutonomous Republic of Crimea: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.