Solar plant: site data
Solar power plant in Barvinok, Khersonskyi Raion, Kherson Oblast
Barvinok: 1,250 kWh per kWp a year, tilt 36° 3° east of south (PVGIS). Exactly the oblast median (1,253). #93 of 109 in the rayon, #397 of 711 in the oblast.
Kherson, the rayon centre, is 23 km away. 41 m above sea level. 21 km away: Bilozerka, the nearest bigger centre, 1,286 — 2.8% less here. Snow and wind from the nearest regional centre in the DBN — Херсон, 23 km. 9.44 m between rows, pitch 13.31 m (latitude 46.8°).
- Yield of 1 kWp
- 1,250kWh/year
- Tilt
- 36°3° east of south
- 10 kW
- 12,496kWh/year
- Row pitch
- 13.31m · GCR 0.36
- T_min
- -42 °Cregion II, south-eastern
- Snow S₀ / wind W₀
- 760 / 480Pa
Ground frame designer
A ground frame for a solar plant: Barvinok
The designer opens with this place’s coordinates, latitude 46.8° for the row spacing and the DBN loads of the nearest regional centre — Херсон, 23 km: snow 760 Pa, wind 480 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
July: 152 kWh/kWp, December: 38 — 4.0 times less.
February: 62 against 60 in the oblast, 3.3% more.
| kWp | A year | July | December |
|---|---|---|---|
| 5 | 6,248 | 760 | 190 |
| 10 | 12,496 | 1,520 | 380 |
| 15 | 18,744 | 2,280 | 570 |
Example: a 10 kW ground frame
For the loads of Kherson: 11.16 kWp, 18 panels, 349 kg of steel, 12 piles, materials ≈ 47,980 UAH.
How these numbers are computed
Nearby
- Zelenyi Hay3 km1,250 kWh/kWp
- Krutyi Yar5 km1,257 kWh/kWp
- Bohorodytske5 km1,251 kWh/kWp
- Novokyyivka7 km1,243 kWh/kWp
- Kyselivka7 km1,257 kWh/kWp
- Shmidtove7 km1,244 kWh/kWp
All places: Khersonskyi RaionKherson Oblast: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.