Solar plant: site data
Solar power plant in Kuzmynets, Kaluskyi Raion, Ivano-Frankivsk Oblast
Kuzmynets: 1,007 kWh per kWp a year, tilt 39° 13° east of south (PVGIS). 8.2% below the oblast median (1,097). #155 of 162 in the rayon, #674 of 700 in the oblast.
Kalush, the rayon centre, is 45 km away. 666 m above sea level — above 500 m the DBN snow and wind are higher. 38 km away: Bohorodchany, the nearest bigger centre, 1,101 — 8.5% less here. Snow and wind from the nearest regional centre in the DBN — Івано-Франківськ, 55 km. 11.46 m between rows, pitch 15.18 m (latitude 48.7°).
- Yield of 1 kWp
- 1,007kWh/year
- Tilt
- 39°13° east of south
- 10 kW
- 10,073kWh/year
- Row pitch
- 15.18m · GCR 0.32
- T_min
- -38 °Cregion IIIA, Carpathian
- Snow S₀ / wind W₀
- 1,410 / 500Pa
Ground frame designer
A ground frame for a solar plant: Kuzmynets
The designer opens with this place’s coordinates, latitude 48.7° for the row spacing and the DBN loads of the nearest regional centre — Івано-Франківськ, 55 km: snow 1,410 Pa, wind 500 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
August: 115 kWh/kWp, December: 39 — 2.9 times less.
May: 105 against 124 in the oblast, 15.3% less.
| kWp | A year | August | December |
|---|---|---|---|
| 5 | 5,037 | 575 | 195 |
| 10 | 10,073 | 1,150 | 390 |
| 15 | 15,110 | 1,725 | 585 |
Snow and wind: Івано-Франківськ
Example: a 10 kW ground frame
For the loads of Ivano-Frankivsk: 11.16 kWp, 18 panels, 410 kg of steel, 16 piles, materials ≈ 54,212 UAH.
How these numbers are computed
Nearby
- Osmoloda4 km971 kWh/kWp
- Hrynkiv4 km1,040 kWh/kWp
- Lazy7 km1,040 kWh/kWp
- Babske9 km1,042 kWh/kWp
- Lypovytsia9 km1,030 kWh/kWp
- Yasen11 km1,059 kWh/kWp
All places: Kaluskyi RaionIvano-Frankivsk Oblast: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.