Spain: solar plant site data

Solar power plant in Sant Cugat del Vallès, Spain: yield, tilt angle and row spacing

Sant Cugat del Vallès: 1,552 kWh per kWp a year at the optimal tilt of 38°, 2° west of south (PVGIS). 3.9% below the median of the main cities of Spain (1,615). #120 of 147 main cities of Spain by yield. For comparison, Kyiv: 1,114 kWh/kWp — 39.3% more here.

Sant Cugat del Vallès is in the province of Barcelona, Catalonia. Population 79,253 (GeoNames). 121 m above sea level. 8 km away: Sabadell, the nearest bigger city, 1,590 kWh/kWp — 2.4% less here. 7.32 m between rows, pitch 11.09 m, GCR 0.43 (latitude 41.5°).

Yield of 1 kWp
1,552kWh/year
Tilt
38°2° west of south
10 kW
15,520kWh/year
Row pitch
11.09m · GCR 0.43
Rank in the country
120of 147 cities

Ground frame designer

A ground frame for a solar plant: Sant Cugat del Vallès

Latitude 41.5°: the tilt and the row pitch follow it. Enter the snow and wind for Spain in the designer, by the national annex to the Eurocode.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

112Jan110Feb136Mar138Apr151May150Jun157Jul150Aug128Sep115Oct101Nov104Dec

July: 157 kWh/kWp, November: 101 — 1.6 times less.

September: 128 against the median of 143 for the main cities of Spain, 10.5% less.

Sant Cugat del Vallès: plants, kWh
kWpA yearJulyNovember
57,760785505
1015,5201,5701,010
1523,2802,3551,515

Snow and wind loads

Snow and wind loads for a site in Spain follow CTE DB SE-AE (Spain’s Código Técnico de la Edificación) and, where the Eurocodes are applied, UNE-EN 1991-1-3 and UNE-EN 1991-1-4 with the Spanish National Annex. Solispec computes loads by the Ukrainian DBN V.1.2-2 only, so this page shows no snow or wind values for Spain: enter the characteristic values from these documents in the designer’s «Own snow S0» and «Own wind W0» fields.

The frame calculation for such a site is preliminary: before installation it must be checked by an engineer who works to the country’s standards.

Nearby cities

Spain: all cities and regions

Sources

Preliminary calculation: a design needs an engineer’s check.