Spain: solar plant site data

Solar power plant in San Sebastián, Spain: yield, tilt angle and row spacing

San Sebastián: 1,177 kWh per kWp a year at the optimal tilt of 37°, 3° west of south (PVGIS). 27.1% below the median of the main cities of Spain (1,615). #143 of 147 main cities of Spain by yield. For comparison, Kyiv: 1,114 kWh/kWp — 5.7% more here.

San Sebastián is in the province of Gipuzkoa, Basque Country. Population 185,357 (GeoNames). 17 m above sea level. 61 km away: Pamplona, the nearest bigger city, 1,404 kWh/kWp — 16.1% less here. 7.88 m between rows, pitch 11.70 m, GCR 0.41 (latitude 43.3°).

Yield of 1 kWp
1,177kWh/year
Tilt
37°3° west of south
10 kW
11,773kWh/year
Row pitch
11.70m · GCR 0.41
Rank in the country
143of 147 cities

Ground frame designer

A ground frame for a solar plant: San Sebastián

Latitude 43.3°: the tilt and the row pitch follow it. Enter the snow and wind for Spain in the designer, by the national annex to the Eurocode.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

63Jan79Feb104Mar111Apr119May114Jun122Jul124Aug116Sep95Oct66Nov63Dec

August: 124 kWh/kWp, January: 63 — 2.0 times less.

January: 63 against the median of 109 for the main cities of Spain, 42.2% less.

San Sebastián: plants, kWh
kWpA yearAugustJanuary
55,887620315
1011,7731,240630
1517,6601,860945

Fixed tilt facing south

What a table yields at another tilt than the optimal 37° — for roofs and frames with a standard slope.

San Sebastián: yield at a fixed tilt, kWh/kWp
TiltA yearAgainst the optimum
37° (optimum)1,177—
15°1,114−5.4%
30°1,171−0.6%
45°1,169−0.7%
90°808−31.4%

Snow and wind loads

Snow and wind loads for a site in Spain follow CTE DB SE-AE (Spain’s Código Técnico de la Edificación) and, where the Eurocodes are applied, UNE-EN 1991-1-3 and UNE-EN 1991-1-4 with the Spanish National Annex. Solispec computes loads by the Ukrainian DBN V.1.2-2 only, so this page shows no snow or wind values for Spain: enter the characteristic values from these documents in the designer’s «Own snow S0» and «Own wind W0» fields.

The frame calculation for such a site is preliminary: before installation it must be checked by an engineer who works to the country’s standards.

Nearby cities

Spain: all cities and regions

Sources

Preliminary calculation: a design needs an engineer’s check.