Spain: solar plant site data

Solar power plant in El Puerto de Santa María, Spain: yield, tilt angle and row spacing

El Puerto de Santa María: 1,733 kWh per kWp a year at the optimal tilt of 34°, 3° west of south (PVGIS). 7.3% above the median of the main cities of Spain (1,615). #12 of 147 main cities of Spain by yield. For comparison, Kyiv: 1,114 kWh/kWp — 55.5% more here.

El Puerto de Santa María is in the province of Cádiz, Andalusia. Population 88,364 (GeoNames). 11 m above sea level. 9 km away: Cadiz, the nearest bigger city, 1,707 kWh/kWp — 1.5% more here. 5.29 m between rows, pitch 9.26 m, GCR 0.52 (latitude 36.6°).

Yield of 1 kWp
1,733kWh/year
Tilt
34°3° west of south
10 kW
17,328kWh/year
Row pitch
9.26m · GCR 0.52
Rank in the country
12of 147 cities

Ground frame designer

A ground frame for a solar plant: El Puerto de Santa María

Latitude 36.6°: the tilt and the row pitch follow it. Enter the snow and wind for Spain in the designer, by the national annex to the Eurocode.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

121Jan121Feb146Mar154Apr167May163Jun173Jul169Aug152Sep138Oct115Nov113Dec

July: 173 kWh/kWp, December: 113 — 1.5 times less.

November: 115 against the median of 103 for the main cities of Spain, 11.7% more.

El Puerto de Santa María: plants, kWh
kWpA yearJulyDecember
58,664865565
1017,3281,7301,130
1525,9922,5951,695

Snow and wind loads

Snow and wind loads for a site in Spain follow CTE DB SE-AE (Spain’s Código Técnico de la Edificación) and, where the Eurocodes are applied, UNE-EN 1991-1-3 and UNE-EN 1991-1-4 with the Spanish National Annex. Solispec computes loads by the Ukrainian DBN V.1.2-2 only, so this page shows no snow or wind values for Spain: enter the characteristic values from these documents in the designer’s «Own snow S0» and «Own wind W0» fields.

The frame calculation for such a site is preliminary: before installation it must be checked by an engineer who works to the country’s standards.

Nearby cities

Spain: all cities and regions

Sources

Preliminary calculation: a design needs an engineer’s check.