Spain: solar plant site data
Solar power plant in Calvià, Spain: yield, tilt angle and row spacing
Calvià: 1,575 kWh per kWp a year at the optimal tilt of 34°, 8° west of south (PVGIS). 2.5% below the median of the main cities of Spain (1,615). #108 of 147 main cities of Spain by yield. For comparison, Kyiv: 1,114 kWh/kWp — 41.4% more here.
Calvià is in Balearic Islands. Population 51,774 (GeoNames). 125 m above sea level. 12 km away: Palma, the nearest bigger city, 1,598 kWh/kWp — 1.5% less here. 6.06 m between rows, pitch 10.03 m, GCR 0.48 (latitude 39.6°).
- Yield of 1 kWp
- 1,575kWh/year
- Tilt
- 34°8° west of south
- 10 kW
- 15,747kWh/year
- Row pitch
- 10.03m · GCR 0.48
- Rank in the country
- 108of 147 cities
Ground frame designer
A ground frame for a solar plant: Calvià
Latitude 39.6°: the tilt and the row pitch follow it. Enter the snow and wind for Spain in the designer, by the national annex to the Eurocode.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
July: 168 kWh/kWp, December: 91 — 1.8 times less.
December: 91 against the median of 103 for the main cities of Spain, 11.7% less.
| kWp | A year | July | December |
|---|---|---|---|
| 5 | 7,874 | 840 | 455 |
| 10 | 15,747 | 1,680 | 910 |
| 15 | 23,621 | 2,520 | 1,365 |
Snow and wind loads
Snow and wind loads for a site in Spain follow CTE DB SE-AE (Spain’s Código Técnico de la Edificación) and, where the Eurocodes are applied, UNE-EN 1991-1-3 and UNE-EN 1991-1-4 with the Spanish National Annex. Solispec computes loads by the Ukrainian DBN V.1.2-2 only, so this page shows no snow or wind values for Spain: enter the characteristic values from these documents in the designer’s «Own snow S0» and «Own wind W0» fields.
The frame calculation for such a site is preliminary: before installation it must be checked by an engineer who works to the country’s standards.
Nearby cities
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation, population and divisions (changed)
- Where to take snow and wind loads from: CTE DB SE-AE
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.