Germany: solar plant site data
Solar power plant in Pforzheim, Germany: yield, tilt angle and row spacing
Pforzheim: 1,088 kWh per kWp a year at the optimal tilt of 37°, 6° west of south (PVGIS). 4.1% above the median of the main cities of Germany (1,045). #46 of 193 main cities of Germany by yield. For comparison, Kyiv: 1,114 kWh/kWp — 2.4% less here.
Pforzheim is in Baden-Württemberg. Population 119,313 (GeoNames). 256 m above sea level. 26 km away: Karlsruhe, the nearest bigger city, 1,135 kWh/kWp — 4.2% less here. 11.12 m between rows, pitch 14.94 m, GCR 0.32 (latitude 48.9°).
- Yield of 1 kWp
- 1,088kWh/year
- Tilt
- 37°6° west of south
- 10 kW
- 10,876kWh/year
- Row pitch
- 14.94m · GCR 0.32
- Rank in the country
- 46of 193 cities
Ground frame designer
A ground frame for a solar plant: Pforzheim
Latitude 48.9°: the tilt and the row pitch follow it. Enter the snow and wind for Germany in the designer, by the national annex to the Eurocode.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
July: 130 kWh/kWp, December: 39 — 3.3 times less.
December: 39 against the median of 30 for the main cities of Germany, 30.0% more.
| kWp | A year | July | December |
|---|---|---|---|
| 5 | 5,438 | 650 | 195 |
| 10 | 10,876 | 1,300 | 390 |
| 15 | 16,314 | 1,950 | 585 |
Snow and wind loads
Snow and wind loads for a site in Germany follow DIN EN 1991-1-3/NA (snow load zone, Schneelastzone) and DIN EN 1991-1-4/NA (wind zone, Windzone). Solispec computes loads by the Ukrainian DBN V.1.2-2 only, so this page shows no snow or wind values for Germany: enter the characteristic values from these documents in the designer’s «Own snow S0» and «Own wind W0» fields.
The frame calculation for such a site is preliminary: before installation it must be checked by an engineer who works to the country’s standards.
Nearby cities
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation, population and divisions (changed)
- Where to take snow and wind loads from: DIN EN 1991-1-3/NA, DIN EN 1991-1-4/NA
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.