Solar plant: site data
Solar power plant in Orlykivka, Novhorod-Siverskyi Raion, Chernihiv Oblast
Orlykivka: 1,064 kWh per kWp a year, tilt 39° 3° east of south (PVGIS). 4.0% below the oblast median (1,108). #243 of 247 in the rayon, #1539 of 1558 in the oblast.
Novhorod-Siverskyi, the rayon centre, is 58 km away. 127 m above sea level. 35 km away: Koryukivka, the nearest bigger centre, 1,085 — 1.9% less here. Snow and wind from the nearest regional centre in the DBN — Чернігів, 100 km. 15.02 m between rows, pitch 18.74 m (latitude 52.1°).
- Yield of 1 kWp
- 1,064kWh/year
- Tilt
- 39°3° east of south
- 10 kW
- 10,638kWh/year
- Row pitch
- 18.74m · GCR 0.26
- T_min
- -40 °Cregion I, north-western
- Snow S₀ / wind W₀
- 1,720 / 410Pa
Ground frame designer
A ground frame for a solar plant: Orlykivka
The designer opens with this place’s coordinates, latitude 52.1° for the row spacing and the DBN loads of the nearest regional centre — Чернігів, 100 km: snow 1,720 Pa, wind 410 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
June: 136 kWh/kWp, December: 24 — 5.7 times less.
November: 30 against 33 in the oblast, 9.1% less.
| kWp | A year | June | December |
|---|---|---|---|
| 5 | 5,319 | 680 | 120 |
| 10 | 10,638 | 1,360 | 240 |
| 15 | 15,957 | 2,040 | 360 |
Example: a 10 kW ground frame
For the loads of Chernihiv: 11.16 kWp, 18 panels, 389 kg of steel, 12 piles, materials ≈ 52,358 UAH.
How these numbers are computed
Nearby
- Khandobokivka5 km1,070 kWh/kWp
- Topolivka5 km1,085 kWh/kWp
- Mkhy7 km1,060 kWh/kWp
- Pohoriltsi7 km1,090 kWh/kWp
- Baranivka8 km1,060 kWh/kWp
- Bleshnia8 km1,055 kWh/kWp
All places: Novhorod-Siverskyi RaionChernihiv Oblast: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.