Solar plant: site data

Solar power plant in Bleshnia, Novhorod-Siverskyi Raion, Chernihiv Oblast

Bleshnia: 1,055 kWh per kWp a year, tilt 39° 3° east of south (PVGIS). 4.8% below the oblast median (1,108). #247 of 247 in the rayon, #1558 of 1558 in the oblast.

Novhorod-Siverskyi, the rayon centre, is 64 km away. 116 m above sea level. 40 km away: Koryukivka, the nearest bigger centre, 1,085 — 2.7% less here. Snow and wind from the nearest regional centre in the DBN — Чернігів, 102 km. 15.10 m between rows, pitch 18.82 m (latitude 52.1°).

Yield of 1 kWp
1,055kWh/year
Tilt
39°3° east of south
10 kW
10,549kWh/year
Row pitch
18.82m · GCR 0.25
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,720 / 410Pa

Ground frame designer

A ground frame for a solar plant: Bleshnia

The designer opens with this place’s coordinates, latitude 52.1° for the row spacing and the DBN loads of the nearest regional centre — Чернігів, 102 km: snow 1,720 Pa, wind 410 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

36Jan56Feb95Mar110Apr134May135Jun133Jul131Aug104Sep68Oct29Nov24Dec

June: 135 kWh/kWp, December: 24 — 5.6 times less.

November: 29 against 33 in the oblast, 12.1% less.

Bleshnia: plants, kWh
kWpA yearJuneDecember
55,275675120
1010,5491,350240
1515,8242,025360

Snow and wind: Чернігів

Example: a 10 kW ground frame

For the loads of Chernihiv: 11.16 kWp, 18 panels, 389 kg of steel, 12 piles, materials ≈ 52,358 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Novhorod-Siverskyi RaionChernihiv Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.