Solar power plant in Pedynivka, Zvenyhorodskyi Raion, Cherkasy Oblast
Pedynivka: 1,143 kWh per kWp a year, tilt 36° 2° east of south (PVGIS). Exactly the oblast median (1,144). #89 of 197 in the rayon, #407 of 731 in the oblast.
Shpola, the rayon centre, is 32 km away. 185 m above sea level. 18 km away: Zvenyhorodka, the nearest bigger centre, the same 1,145. Snow and wind from the nearest regional centre in the DBN — Черкаси, 75 km. 11.13 m between rows, pitch 15.00 m (latitude 49.2°).
- Yield of 1 kWp
- 1,143kWh/year
- Tilt
- 36°2° east of south
- 10 kW
- 11,428kWh/year
- Row pitch
- 15.00m · GCR 0.32
- T_min
- -40 °Cregion I, north-western
- Snow S₀ / wind W₀
- 1,520 / 420Pa
Ground frame designer
A ground frame for a solar plant: Pedynivka
The designer opens with this place’s coordinates, latitude 49.2° for the row spacing and the DBN loads of the nearest regional centre — Черкаси, 75 km: snow 1,520 Pa, wind 420 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
July: 148 kWh/kWp, December: 27 — 5.5 times less.
December: 27 against 28 in the oblast, 3.6% less.
| kWp | A year | July | December |
|---|---|---|---|
| 5 | 5,714 | 740 | 135 |
| 10 | 11,428 | 1,480 | 270 |
| 15 | 17,142 | 2,220 | 405 |
Example: a 10 kW ground frame
For the loads of Cherkasy: 11.16 kWp, 18 panels, 372 kg of steel, 12 piles, materials ≈ 49,705 UAH.
How these numbers are computed
Nearby
- Shevchenkove3 km1,138 kWh/kWp
- Hnylets4 km1,146 kWh/kWp
- Budyshche5 km1,141 kWh/kWp
- Sehedyntsi7 km1,145 kWh/kWp
- Moryntsi7 km1,144 kWh/kWp
- Petryky7 km1,145 kWh/kWp
All places: Zvenyhorodskyi RaionCherkasy Oblast: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.