Section of the table from the Solispec engine (median zone — Cherkasy)

Trina

Ground frame for 40 Trina Vertex S+ TSM-500NEG18R.28 panels (2×20)

2 rows of 20 panels, 20.00 kW. The Solispec engine chose the profiles, the frame pitch and the footings for three snow and wind zones: Kherson has the lowest load of the regional centres, Cherkasy the median, Chernihiv the highest.

Power
20.00kW
Steel
630.8kg
Posts
22
Bolts
252
Materials
83,405₴
Yield
22,776kWh/year

Figures for the median zone (Cherkasy); all three zones are in the table below.

Ground frame designer

Open this frame in the builder

The builder opens with the Trina Vertex S+ TSM-500NEG18R.28 panel and the 2 × 20 layout; site — Cherkasy. Change the site, the tilt or the profiles and the checks and estimate are recalculated.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Three snow and wind zones

The same table designed for three regional centres: with the lowest, the median and the highest combined snow and wind load under DBN V.1.2-2:2006. For another site, open the frame in the builder.

ParameterLow loadKherson · S₀ 760 · W₀ 480Median loadCherkasy · S₀ 1,520 · W₀ 420High loadChernihiv · S₀ 1,720 · W₀ 410
PostsTube 60×60×2Tube 60×60×2Tube 60×60×2
RaftersC-channel 60×40×2C-channel 60×40×2Tube 60×60×2
Purlins and bracesC-channel 60×40×2C-channel 60×40×2C-channel 60×40×2
Frames10 frames, pitch up to 2,490 mm11 frames, pitch up to 2,250 mm11 frames, pitch up to 2,250 mm
Posts202222
Footings (bored concrete)20 pcs, Ø400 mm, depth 1,100 mm22 pcs, Ø300 mm, depth 1,300 mm22 pcs, Ø300 mm, depth 1,300 mm
Concrete3.04 m³2.22 m³2.22 m³
Tilt30°30°30°
Panel bottom / post top600 / 1,981 mm600 / 1,981 mm600 / 1,981 mm
Panel field size23,200 × 2,571 mm23,200 × 2,571 mm23,200 × 2,571 mm
Row spacing between tables (no shade on 21 December)8,850 mm at noon · 9,940 mm ±2 h9,800 mm at noon · 11,320 mm ±2 h10,740 mm at noon · 12,770 mm ±2 h
Steel585.6 kg630.8 kg666.6 kg
BoltsM10 — 158, M8 — 84M10 — 168, M8 — 84M10 — 168, M8 — 84
Panel clampsend 8, middle 76end 8, middle 76end 8, middle 76
Materials82,656 UAH83,405 UAH87,110 UAH
With installation and delivery133,616 UAH134,337 UAH138,537 UAH
Per 1 kW6,681 UAH/kW6,717 UAH/kW6,927 UAH/kW
Yield1,266 kWh/kW · 25,329 kWh/year1,139 kWh/kW · 22,776 kWh/year1,043 kWh/kW · 20,863 kWh/year
Strength σ/fy82%92%99%
Deflection / (L/200)81%82%88%
Rafter strength79%98%69%
Post utilisation16%20%21%
Utilisation97%91%89%
Depth vs frost depthokokok
Checks overallwith a cautionwith a cautionwith a caution

Checks and cautions

Member utilisation as the engine computes it. Cautions are checks that pass, but with a small margin.

  • Max. frame pitch, mmThe purlins between the frames are used above 80 % (strength or deflection): the structure passes, but the margin is small. A shorter frame pitch or a deeper purlin gives more margin.Kherson: Frame spacing 2 490 mm, 10 frames. Purlin C-channel 60×40×2: strength 82%, deflection 81% of L/200 (snow on panel 489 Pa).Cherkasy: Frame spacing 2 250 mm, 11 frames. Purlin C-channel 60×40×2: strength 92%, deflection 82% of L/200 (snow on panel 977 Pa).Chernihiv: Frame spacing 2 250 mm, 11 frames. Purlin C-channel 60×40×2: strength 99%, deflection 88% of L/200 (snow on panel 1 106 Pa).
  • Embedment, mmThe footing resists wind uplift at above 80 % utilisation, or it is shallower than the frost depth. The soil resistance in the calculation is an estimate — check the soil on site.Kherson: Foundation Ø400 × 1 100: 0.138 m³ of concrete per post. Wind uplift on the front post ≈ 12.9 kN (with γ=1.5) vs ≈ 13.4 kN (concrete weight + soil friction, estimate) → 97%.Cherkasy: Foundation Ø300 × 1 300: 0.092 m³ of concrete per post. Wind uplift on the front post ≈ 10.2 kN (with γ=1.5) vs ≈ 11.2 kN (concrete weight + soil friction, estimate) → 91%.Chernihiv: Foundation Ø300 × 1 300: 0.092 m³ of concrete per post. Wind uplift on the front post ≈ 10.0 kN (with γ=1.5) vs ≈ 11.2 kN (concrete weight + soil friction, estimate) → 89%.
  • Rafter profileThe rafter is used above 80 %, or the frame's posts stand far apart: the structure passes, but the margin is small.Cherkasy: Rafter C-channel 60×40×2: span between posts 1 892, cantilever 685 mm → strength 98%.

Bill of materials

The parts of one table for the median zone (Cherkasy): mark, name, profile, cut length, quantity.

MarkPartProfileLength, mmQuantity
П1Front postTube 60×60×22,36011
П2Rear postTube 60×60×23,30611
Кр1Rafter (inclined beam)C-channel 60×40×23,26211
Пк1Frame strutC-channel 60×40×21,55111
Х1Longitudinal brace (cross)C-channel 60×40×22,6394
Р1Purlin (rail)C-channel 60×40×26,0002
Р2Purlin (rail)C-channel 60×40×26,0002
Р3Purlin (rail)C-channel 60×40×26,0002
Р4Purlin (rail)C-channel 60×40×26,0002
Р5Purlin (rail)C-channel 60×40×26,0002
Р6Purlin (rail)C-channel 60×40×26,0002
Р7Purlin (rail)C-channel 60×40×25,2002
Р8Purlin (rail)C-channel 60×40×25,2002
—Bolt M10×25 set · purlins, braces, connectors——50
—Bolt M10×80 set · purlin to rafter——44
—Bolt M10×90 set · strut to post — through spacer inserts——11
—Bolt M10×120 set · post–rafter——44
—Bolt M10×130 set · strut to rafter — through spacer inserts——11
—Bolt M10×150 set · brace to post — through spacer inserts——8
—End clamp 30 mm——8
—Mid clamp (30–40 mm)——76
—Bolt M8×50 + channel nut——84
—Concrete for 22 posts, Ø300×1300——2.22 m³

Profile cutting

40 bars of 6,000 mm, 218.6 m of profile in total.

  • Tube 60×60×211 bars
  • C-channel 60×40×229 bars

Estimated cost

The engine's materials estimate for the median zone (Cherkasy).

Materials
83,405₴
With installation and delivery
134,337₴
Per 1 kW
6,717UAH/kW

Prices are the typical market prices built into the Solispec engine, as of 06.10.2026; no margin, no VAT.

All 23 lines of the engine's estimate, with prices
ItemQuantityPrice, UAHSum, UAH
Tube 60×60×2, stock length 6 000 mm11 bar21013,860
C-channel 60×40×2, stock length 6 000 mm29 bar23040,020
C-channel connector (splice plate L 300)12 pcs901,080
Bolt M10×25 cl. 8.8 set — purlins, braces, connectors67 pcs221,474
Bolt M10×80 cl. 8.8 set — purlin to rafter44 pcs271,188
Bolt M10×90 cl. 8.8 set — strut to post — through spacer inserts11 pcs27297
Bolt M10×120 cl. 8.8 set — post–rafter44 pcs271,188
Bolt M10×130 cl. 8.8 set — strut to rafter — through spacer inserts11 pcs27297
Bolt M10×150 cl. 8.8 set — brace to post — through spacer inserts8 pcs27216
End clamp 30 mm8 pcs35280
Mid clamp (30–40 mm)76 pcs322,432
Bolt M8×50 A2 + spring channel nut M893 pcs141,302
Post base anchor pin (M10 / rebar Ø12)22 pcs20440
Borehole casing (roofing felt / PVC, 300 mm)22 pcs601,320
Crushed stone 20–40 for the bottom of the boreholes0.16 m³900144
Earth electrode: 2 rods Ø16×1.5 m + strip 40×41 set1,5001,500
Wire PV-3 6 mm² green-yellow51 m351,785
Module earthing clip (under the clamp)40 pcs20800
Cable clip, stainless120 pcs5600
Zinc paint / cold galvanising spray 400 ml3 pcs3501,050
Concrete M200 for posts2.22 m³3,8008,436
Rebar Ø10 (4 bars per post)132 m283,696
Spacer inserts / packs — pieces of the same profile (from offcuts): 4 × 71 mm, 11 × 70 mm, 4 × 30 mm, 11 × 10 mm30 pcs00
Materials83,405

Yield

Yield: 1,139 kWh per 1 kW a year, ≈ 22,776 kWh a year in total (median zone, Cherkasy; tilt 30°, the optimum for the latitude is 35.3°).

A preliminary calculation; a design needs an engineer's check. Snow and wind per DBN V.1.2-2:2006 for the regional centre; profiles, footings and estimate by the Solispec engine 0.12.0.