Section of the table from the Solispec engine (median zone — Cherkasy)

Huasun

Ground frame for 10 Huasun Himalaya G12 HS-210-B132DS720 (HJT) panels (2×5)

2 rows of 5 panels, 7.20 kW. The Solispec engine chose the profiles, the frame pitch and the footings for three snow and wind zones: Kherson has the lowest load of the regional centres, Cherkasy the median, Chernihiv the highest.

Power
7.20kW
Steel
254.9kg
Posts
8
Bolts
90
Materials
33,758₴
Yield
8,199kWh/year

Figures for the median zone (Cherkasy); all three zones are in the table below.

Ground frame designer

Open this frame in the builder

The builder opens with the Huasun Himalaya G12 HS-210-B132DS720 (HJT) panel and the 2 × 5 layout; site — Cherkasy. Change the site, the tilt or the profiles and the checks and estimate are recalculated.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Three snow and wind zones

The same table designed for three regional centres: with the lowest, the median and the highest combined snow and wind load under DBN V.1.2-2:2006. For another site, open the frame in the builder.

ParameterLow loadKherson · S₀ 760 · W₀ 480Median loadCherkasy · S₀ 1,520 · W₀ 420High loadChernihiv · S₀ 1,720 · W₀ 410
PostsTube 60×60×2Tube 60×60×2Tube 60×60×2
RaftersTube 60×60×2Tube 60×60×2Tube 60×60×2
Purlins and bracesC-channel 41×41×2.5C-channel 60×40×2C-channel 60×40×2
Frames5 frames, pitch up to 1,570 mm4 frames, pitch up to 2,040 mm5 frames, pitch up to 1,570 mm
Posts10810
Footings (bored concrete)10 pcs, Ø350 mm, depth 1,100 mm8 pcs, Ø400 mm, depth 1,100 mm10 pcs, Ø300 mm, depth 1,300 mm
Concrete1.16 m³1.22 m³1.01 m³
Tilt30°30°30°
Panel bottom / post top600 / 2,305 mm600 / 2,289 mm600 / 2,289 mm
Panel field size6,735 × 3,095 mm6,735 × 3,105 mm6,735 × 3,105 mm
Row spacing between tables (no shade on 21 December)10,740 mm at noon · 12,080 mm ±2 h11,900 mm at noon · 13,750 mm ±2 h13,050 mm at noon · 15,510 mm ±2 h
Steel291.4 kg254.9 kg297.7 kg
BoltsM10 — 76, M8 — 24M10 — 66, M8 — 24M10 — 76, M8 — 24
Panel clampsend 8, middle 16end 8, middle 16end 8, middle 16
Materials35,717 UAH33,758 UAH40,564 UAH
With installation and delivery55,152 UAH53,220 UAH59,999 UAH
Per 1 kW7,660 UAH/kW7,392 UAH/kW8,333 UAH/kW
Yield1,266 kWh/kW · 9,118 kWh/year1,139 kWh/kW · 8,199 kWh/year1,043 kWh/kW · 7,511 kWh/year
Strength σ/fy73%94%60%
Deflection / (L/200)57%75%37%
Rafter strength48%85%71%
Post utilisation15%26%21%
Utilisation92%89%80%
Depth vs frost depthokokok
Checks overallwith a cautionwith a cautionpasses

Checks and cautions

Member utilisation as the engine computes it. Cautions are checks that pass, but with a small margin.

  • Embedment, mmThe footing resists wind uplift at above 80 % utilisation, or it is shallower than the frost depth. The soil resistance in the calculation is an estimate — check the soil on site.Kherson: Foundation Ø350 × 1 100: 0.106 m³ of concrete per post. Wind uplift on the front post ≈ 10.4 kN (with γ=1.5) vs ≈ 11.4 kN (concrete weight + soil friction, estimate) → 92%.Cherkasy: Foundation Ø400 × 1 100: 0.138 m³ of concrete per post. Wind uplift on the front post ≈ 11.8 kN (with γ=1.5) vs ≈ 13.4 kN (concrete weight + soil friction, estimate) → 89%.
  • Max. frame pitch, mmThe purlins between the frames are used above 80 % (strength or deflection): the structure passes, but the margin is small. A shorter frame pitch or a deeper purlin gives more margin.Cherkasy: Frame spacing 2 040 mm, 4 frames. Purlin C-channel 60×40×2: strength 94%, deflection 75% of L/200 (snow on panel 977 Pa).
  • Rafter profileThe rafter is used above 80 %, or the frame's posts stand far apart: the structure passes, but the margin is small.Cherkasy: Rafter Tube 60×60×2: span between posts 2 278, cantilever 825 mm → strength 85%.

Bill of materials

The parts of one table for the median zone (Cherkasy): mark, name, profile, cut length, quantity.

MarkPartProfileLength, mmQuantity
П1Front postTube 60×60×22,2744
П2Rear postTube 60×60×23,4144
Кр1Rafter (inclined beam)Tube 60×60×23,9284
Пк1Frame strutC-channel 60×40×21,8204
Х1Longitudinal brace (cross)C-channel 60×40×22,6364
Р1Purlin (rail)C-channel 60×40×26,0002
Р2Purlin (rail)C-channel 60×40×26,0002
Р3Purlin (rail)C-channel 60×40×27352
Р4Purlin (rail)C-channel 60×40×27352
—Bolt M10×140 / M10×80 set · frame and struts / purlins, braces, connectors——54
—Bolt M10×150 set · brace to post, strut to rafter — through spacer inserts——12
—End clamp 35 mm——8
—Mid clamp (30–40 mm)——16
—Bolt M8×55 + channel nut——24
—Concrete for 8 posts, Ø400×1100——1.22 m³

Profile cutting

16 bars of 6,000 mm, 83.2 m of profile in total.

  • Tube 60×60×28 bars
  • C-channel 60×40×28 bars

Estimated cost

The engine's materials estimate for the median zone (Cherkasy).

Materials
33,758₴
With installation and delivery
53,220₴
Per 1 kW
7,392UAH/kW

Prices are the typical market prices built into the Solispec engine, as of 06.10.2026; no margin, no VAT.

All 20 lines of the engine's estimate, with prices
ItemQuantityPrice, UAHSum, UAH
Tube 60×60×2, stock length 6 000 mm8 bar21010,080
C-channel 60×40×2, stock length 6 000 mm8 bar23011,040
C-channel connector (splice plate L 300)4 pcs90360
Bolt M10×140 cl. 8.8 set — frame, struts20 pcs22440
Bolt M10×80 cl. 8.8 set — purlins, braces, connectors41 pcs22902
Bolt M10×150 cl. 8.8 set — strut to rafter, brace to post — through spacer inserts12 pcs27324
End clamp 35 mm8 pcs35280
Mid clamp (30–40 mm)16 pcs32512
Bolt M8×55 A2 + spring channel nut M827 pcs14378
Post base anchor pin (M10 / rebar Ø12)8 pcs20160
Borehole casing (roofing felt / PVC, 300 mm)8 pcs60480
Crushed stone 20–40 for the bottom of the boreholes0.10 m³90090
Earth electrode: 2 rods Ø16×1.5 m + strip 40×41 set1,5001,500
Wire PV-3 6 mm² green-yellow20 m35700
Module earthing clip (under the clamp)10 pcs20200
Cable clip, stainless30 pcs5150
Zinc paint / cold galvanising spray 400 ml1 pcs350350
Concrete M200 for posts1.22 m³3,8004,636
Rebar Ø10 (4 bars per post)42 m281,176
Spacer inserts / packs — pieces of the same profile (from offcuts): 4 × 71 mm, 4 × 70 mm, 4 × 30 mm, 4 × 10 mm16 pcs00
Materials33,758

Yield

Yield: 1,139 kWh per 1 kW a year, ≈ 8,199 kWh a year in total (median zone, Cherkasy; tilt 30°, the optimum for the latitude is 35.3°).

A preliminary calculation; a design needs an engineer's check. Snow and wind per DBN V.1.2-2:2006 for the regional centre; profiles, footings and estimate by the Solispec engine 0.12.0.

Other layouts of this panel

The 2×5 layout with other panels

Next