Mounting solar panels on a roof: slate, metal tile, trapezoidal sheet

Solar panel roof mounting by roof type — what to fix into, how to seal it and what spacing your region's snow and wind need. With a worked example for Kharkiv.

By Solispec editorial11 min read

A solar panel roof mount always goes into the load-bearing structure — the rafters, purlins or battens — never into the roof sheet alone. The roof covering decides the type of attachment and how it is sealed; the spacing of the attachments is decided by your region's snow and wind under DBN V.1.2-2 and by the clamp zones in the panel's datasheet. Below: what connects to what on each roof type, where people most often go wrong, and a worked example for Kharkiv with the numbers of our calculator.

What a pitched-roof mounting system is made of

The set of parts is almost the same on every pitched roof; only the part that passes through the covering changes:

  • The attachment — an M10 hanger bolt with an adapter and an L-bracket, a tile hook or a seam clamp. It is the only part that carries the panels' load into the roof structure.
  • Rails (profiles) — two per row of panels, running along the row. The panels sit on them, and the attachments stand under the rail at a spacing that is a multiple of the rafter spacing.
  • Clamps — mid clamps between neighbouring panels and end clamps at the ends of a row. They press the panel frame onto the rail.
  • Seals — an EPDM washer under the nut, an EPDM pad or flange under the bracket, sealant around the hole. Every penetration of the covering is a potential leak, so sealing matters as much as strength.

The main rule: the rail holds the panel, the attachment holds the rail, and the rafter holds the attachment. If the roof sheet is a load-bearing link in this chain (except on trapezoidal sheet, see below), the design is wrong.

Metal tile

The attachment is an M10×200 hanger bolt with an L-bracket and an EPDM washer, into the rafters. The installation order as the Solispec engine describes it:

  1. Drill the sheet at the crest of the profile with a Ø12 step drill, and a Ø7 pilot hole in the rafter.
  2. Drive the hanger bolt at least 70 mm into the rafter.
  3. Fit the EPDM washer and the sealing nut, compressing the EPDM by about a third. Sealant around the hole.
  4. Level the brackets with their nuts along a string line and tighten to 15–20 N·m.

Typical mistakes: a hole in the trough of the profile where water runs; a bolt that misses the rafter and only catches a batten; an overtightened nut that dents the sheet. Calculations for a typical roof in Kyiv, Lviv and Kharkiv are on the page metal tile mounting.

Slate

The attachment is an M10×200 hanger bolt with an EPDM washer, a cap and sealant, into the rafters or purlins (M10×250 where there is a counter-batten). Slate is brittle, so:

  • drill without hammer action, Ø12–14, at the crest of the corrugation only;
  • do not overtighten the sealing nut — slate cracks;
  • tighten the bracket to 15–20 N·m.

Old slate may contain asbestos. Work in an FFP3 respirator and keep the drilling spot wet.

Assess the sheets before mounting: cracked or brittle slate is better replaced before the plant goes up than after, when the panels have to come off. Details on the page slate mounting.

Trapezoidal sheet

Trapezoidal sheet is the one case where the attachment sits in the sheet itself. Instead of long rails there are mini rails under the panel joints, each on five 6.3×25 self-drilling screws with EPDM washers, with an EPDM pad under the rail. Conditions:

  • steel sheet at least 0.5 mm thick; thinner sheet takes only brackets into the purlins;
  • screws into the top corrugation, never into the sheet overlap;
  • a depth-limited screwdriver: the washer compressed to its edge, the sheet not dented;
  • the mini rails of one row on one line (string line, ±2 mm).

A sheet holds less than a rafter, so trapezoidal sheet has the smallest uplift margin — the example below shows it. Page: trapezoidal sheet mounting.

Bitumen shingles and soft roofing

Bitumen shingles usually lie on OSB, often only 9–12 mm thick. So fix into the rafter: an M10×200 hanger bolt right through (at least 70 mm, Ø7 pilot) with an EPDM flange, or a bracket on two 8×80 screws into the rafter. Fixing into OSB alone is acceptable only for OSB of 18 mm or more and if the bracket's datasheet allows it.

Under a continuous deck, find the rafters by the nails or from the attic. Lift the shingle, apply bitumen mastic and butyl tape under the bracket base, then put the shingle back and glue it down with mastic. Page: bitumen shingle mounting.

Clay and concrete tile

Here the attachment does not drill the covering: an adjustable tile hook is screwed to the rafter with two or three 8×80 screws (Ø5 pilot, at least 60 mm into the rafter). If the rafter sits lower than the batten, pack it with a 40 mm board.

The most common mistake is a hook that presses on the tile, which then cracks under snow. The tile under the hook is trimmed to leave a 3–5 mm gap. The check is simple: press the hook — the tile must not take any load. Keep spare tiles. Page: clay tile mounting.

On a standing seam roof the sheet is not drilled at all — seam clamps matching the seam type (single, double, click) are used. On corrugated bitumen sheet the sheet is not load-bearing: the hanger bolt goes into the rafter, and penetrations may affect the roofing maker's warranty. See standing seam and corrugated bitumen sheet.

Flat roof: ballast or anchors

On a flat roof the panels stand on tilted supports, and there are two ways:

  • Ballast — concrete blocks hold the supports down and the roof membrane is not pierced. Ballast is checked for three things: wind uplift, sliding and overturning. Separately: can the roof slab carry it — the ballast plus snow must not exceed the roof's allowed load from its survey or design.
  • Anchors into the roof slab — less weight on the roof, but every penetration needs waterproofing, and the anchor needs a calculation on its maker's data. Our calculator does not cover anchored systems.

Which governs, uplift or sliding, cannot be guessed in advance. For a row of 5 panels at 15° in the middle of the roof of a 6 m high building in Kyiv, the ballast calculator gives: about 290 kg is enough against uplift, but with sliding (friction 0.4, with the safety factor) about 590 kg per row is needed. Light 2PB10 lintels give 516 kg and fail; BR 100.30.15 road kerbs give 1,296 kg and pass. The calculation takes a reference friction between support and roof covering, so confirm it for your roof. More on the page flat roof mounting.

Attachment spacing: snow, wind and the panel's clamp zones

The spacing of attachments along a rail is not a "standard 1.2 m". Four things decide it:

  1. Rafter spacing. An attachment stands only on a rafter, so its spacing is a multiple of the rafter spacing: every rafter, every second one and so on.
  2. The covering. The calculator has a maximum spacing for each covering: metal tile 1,200 mm, concrete tile 1,100 mm, clay tile, bitumen shingles, slate, standing seam and corrugated bitumen sheet 1,000 mm, and never more than 1,500 mm.
  3. Wind near the roof edges. DBN V.1.2-2 (clause 9.16, Change 2) requires the roof's fastenings to take a local negative pressure: coefficient 2 in a strip e/10 wide along the roof's outline and 3.5 in the corners. If the array reaches into that strip, the maximum spacing drops by a factor of 1.5. If the snow on the slope exceeds 1.5 kPa, the spacing is at most 800 mm.
  4. The rail's cantilever beyond the last attachment — no more than a third of the span and no more than 400 mm.

Then each attachment is checked for two forces: wind uplift (γn·cp·Wm·A/n) and pressure from self-weight and snow (γn·(1.05·G + Sm·cos²α)·A/n), where A is the panel area and n the number of attachments. Both are compared with the attachment's capacity on that covering. The rail is checked separately, for bending and deflection.

Clamp zones. The panel maker states in the datasheet where along the long side of the frame it may be clamped. The calculator places the rails about L/4.5 from the short edges: for a 2,350 mm panel that is about 520 mm. If your panel has other zones, the rails go where the datasheet says, because clamping outside the zone can void the warranty and overload the frame.

Snow and wind for your regional centre are on the page snow and wind loads, or calculate them for an address in the snow and wind calculator.

Example: metal tile in Kharkiv

The inputs are those of the attachments calculator: a 30° slope, rafters every 600 mm, 2 rows of 10 panels of 2,350×1,100 mm, a 6 m building, terrain II, 150 m above sea level. For Kharkiv the DBN gives S₀ = 1,600 Pa and W₀ = 430 Pa; at 6 m the design wind is Wm ≈ 318 Pa.

The result:

  • The array sits at the calculator's setbacks — 400 mm from the eaves, 300 mm from the ridge, 400 mm from the gable — so it is in the corner zone: cp = 3.5. The maximum spacing for metal tile is 1,200 mm, 800 mm with the zone. The largest multiple of 600 is 600 mm: an attachment on every rafter.
  • 18 attachments per rail, 4 rails — 72 attachments. The rail's cantilever is 198 mm.
  • Uplift per attachment: 3.5 × 318 Pa × 51.7 m² / 72 ≈ 0.80 kN against a reference capacity of 3.0 kN.
  • Pressure per attachment ≈ 0.84 kN against 2.5 kN. The rail is at 11 % of its capacity.

How the result changes:

  • Rafters every 400 mm: an attachment on every second rafter (800 mm spacing), 52 pcs, uplift 1.11 kN, pressure 1.16 kN, rail at 20 %.
  • Rafters every 900 mm: on every rafter, 48 pcs, uplift 1.20 kN, pressure 1.26 kN, rail at 25 %.
  • Trapezoidal sheet on the same roof: 44 mini rails, uplift 1.31 kN against a reference 1.5 kN — the margin is already small.
  • Trapezoidal sheet in Odesa: less snow (S₀ = 880 Pa) but more wind (W₀ = 460 Pa), and the uplift grows to 1.40 kN. On light coverings wind decides, not snow.

The capacity here is the reference value the calculator takes. For your own attachment, use the value from its datasheet.

DIY solar panel roof mounting: a checklist

If you mount the panels yourself, go through the list before you drill the roof:

  • The rafters are found, their spacing and section measured; the rafter is sound, with no rot.
  • Snow and wind are taken for the house's location, not "for the region by eye".
  • The attachment spacing is a multiple of the rafter spacing and no larger than the maximum for the covering and the roof zone.
  • Uplift and pressure per attachment are below the datasheet capacity.
  • The rails are in the clamp zones of the panel's datasheet; the cantilever is no more than a third of the span.
  • Holes are at the crest of the profile, with EPDM and sealant; nuts are not overtightened.
  • Trapezoidal sheet is 0.5 mm or more, screws into the top corrugation, not into the overlap.
  • Tile under a hook has a 3–5 mm gap.
  • Slate: drilling without hammer action, a respirator, a wet spot.
  • Work at height with fall protection.

The calculation is preliminary. A qualified engineer must check it before installation.

Frequently asked questions

Can solar panels be fixed to the roof sheet alone?

On metal tile, slate, corrugated bitumen sheet, bitumen shingles and clay tile — no: the attachment must go into a rafter or purlin. The exception is steel trapezoidal sheet of 0.5 mm or more on mini rails with five screws into the top corrugation, and even there the uplift margin is the smallest.

What attachment spacing do solar panels on a roof need?

It is a multiple of the rafter spacing, limited by the covering and by the wind near the roof edges. For metal tile the maximum is 1,200 mm; near the roof edges it drops by a factor of 1.5, and with more than 1.5 kPa of snow on the slope it is at most 800 mm. The exact value for your roof comes from the attachments calculator.

How many attachments does one panel need?

That depends on the rafter spacing, not on the panel. In the Kharkiv example, 20 panels need 72 attachments with rafters every 600 mm and 52 with rafters every 400 mm (an attachment on every second one).

Which is better on a flat roof — ballast or anchors?

Ballast does not pierce the roof but adds weight, so first find out the roof slab's allowed load. Anchors are lighter, but every penetration needs waterproofing. Ballast is checked for uplift, sliding and overturning — and sliding often needs more weight than uplift.

Do I need a calculation if I install the plant myself?

Yes. Snow and wind loads are the same for an installer and a home owner, and a mistake shows in winter, when it is too late. Work out the spacing in the calculator; a full project with drawings and a parts list can be made in Solispec. For ground-mounted structures, see how a ground-mount truss is checked.

StructuresNorms

News and design tips

What’s new in Solispec, changes to the standards and practical tips on designing solar power systems.

What interests you

How we handle your data: privacy policy.

Ground frame designer

Design the ground frame for your solar plant

Solispec picks the profiles and posts, checks the frame against snow and wind to the DBN and prices it down to the last bolt.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate