Solar plant: site data

Solar power plant in Zaboroche, Korostenskyi Raion, Zhytomyr Oblast

Zaboroche: 1,077 kWh per kWp a year, tilt 38° 4° east of south (PVGIS). 2.4% below the oblast median (1,104). #434 of 560 in the rayon, #1556 of 1700 in the oblast.

Korosten, the rayon centre, is 73 km away. 187 m above sea level. 63 km away: Zvyahel, the nearest bigger centre, 1,101 — 2.2% less here. Snow and wind from the nearest regional centre in the DBN — Рівне, 115 km. 13.57 m between rows, pitch 17.34 m (latitude 51.2°).

Yield of 1 kWp
1,077kWh/year
Tilt
38°4° east of south
10 kW
10,774kWh/year
Row pitch
17.34m · GCR 0.28
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,320 / 520Pa

Ground frame designer

A ground frame for a solar plant: Zaboroche

The designer opens with this place’s coordinates, latitude 51.2° for the row spacing and the DBN loads of the nearest regional centre — Рівне, 115 km: snow 1,320 Pa, wind 520 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

34Jan56Feb88Mar116Apr131May137Jun137Jul133Aug109Sep76Oct34Nov26Dec

June: 137 kWh/kWp, December: 26 — 5.3 times less.

October: 76 against 81 in the oblast, 6.2% less.

Zaboroche: plants, kWh
kWpA yearJuneDecember
55,387685130
1010,7741,370260
1516,1612,055390

Snow and wind: Рівне

Example: a 10 kW ground frame

For the loads of Rivne: 11.16 kWp, 18 panels, 415 kg of steel, 16 piles, materials ≈ 55,054 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Korostenskyi RaionZhytomyr Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.