Tsyhanivtsi: 1,150 kWh per kWp a year, tilt 37° 1° west of south (PVGIS). 0.8% above the oblast median (1,141). #52 of 122 in the rayon, #250 of 613 in the oblast.
Uzhhorod, the rayon centre, is 8 km away. 140 m above sea level. 8 km away: Uzhhorod, the nearest bigger centre, 1,171 — 1.8% less here. Snow and wind from the nearest regional centre in the DBN — Ужгород, 8 km. 10.89 m between rows, pitch 14.71 m (latitude 48.6°).
- Yield of 1 kWp
- 1,150kWh/year
- Tilt
- 37°1° west of south
- 10 kW
- 11,497kWh/year
- Row pitch
- 14.71m · GCR 0.33
- T_min
- -32 °Cregion IIIB, Transcarpathian
- Snow S₀ / wind W₀
- 1,340 / 370Pa
Ground frame designer
A ground frame for a solar plant: Tsyhanivtsi
The designer opens with this place’s coordinates, latitude 48.6° for the row spacing and the DBN loads of the nearest regional centre — Ужгород, 8 km: snow 1,340 Pa, wind 370 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
July: 140 kWh/kWp, December: 29 — 4.8 times less.
December: 29 against 31 in the oblast, 6.5% less.
| kWp | A year | July | December |
|---|---|---|---|
| 5 | 5,749 | 700 | 145 |
| 10 | 11,497 | 1,400 | 290 |
| 15 | 17,246 | 2,100 | 435 |
Example: a 10 kW ground frame
For the loads of Uzhhorod: 11.16 kWp, 18 panels, 366 kg of steel, 12 piles, materials ≈ 48,597 UAH.
How these numbers are computed
Nearby
- Velyki Lazy3 km1,155 kWh/kWp
- Strypa4 km1,140 kWh/kWp
- Barvinok4 km1,156 kWh/kWp
- Pidhorb5 km1,176 kWh/kWp
- Baranyntsi5 km1,172 kWh/kWp
- Verkhnya Solotvyna5 km1,138 kWh/kWp
All places: Uzhhorodskyi RaionZakarpattia Oblast: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed