Solar plant: site data

Solar power plant in Sopky, Khustskyi Raion, Zakarpattia Oblast

Sopky: 1,036 kWh per kWp a year, tilt 36° 5° east of south (PVGIS). 9.2% below the oblast median (1,141). #113 of 145 in the rayon, #550 of 613 in the oblast.

Khust, the rayon centre, is 42 km away. 625 m above sea level — above 500 m the DBN snow and wind are higher. 42 km away: Khust, the nearest bigger centre, 978 — 5.9% more here. Snow and wind from the nearest regional centre in the DBN — Ужгород, 85 km. 10.59 m between rows, pitch 14.46 m (latitude 48.5°).

Yield of 1 kWp
1,036kWh/year
Tilt
36°5° east of south
10 kW
10,363kWh/year
Row pitch
14.46m · GCR 0.33
T_min
-38 °Cregion IIIA, Carpathian
Snow S₀ / wind W₀
1,340 / 370Pa

Ground frame designer

A ground frame for a solar plant: Sopky

The designer opens with this place’s coordinates, latitude 48.5° for the row spacing and the DBN loads of the nearest regional centre — Ужгород, 85 km: snow 1,340 Pa, wind 370 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

36Jan58Feb90Mar106Apr117May122Jun129Jul131Aug103Sep80Oct45Nov21Dec

August: 131 kWh/kWp, December: 21 — 6.2 times less.

December: 21 against 31 in the oblast, 32.3% less.

Sopky: plants, kWh
kWpA yearAugustDecember
55,182655105
1010,3631,310210
1515,5451,965315

Snow and wind: Ужгород

Example: a 10 kW ground frame

For the loads of Uzhhorod: 11.16 kWp, 18 panels, 366 kg of steel, 12 piles, materials ≈ 48,597 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Khustskyi RaionZakarpattia Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.