Solar plant: site data

Solar power plant in Podobovets, Khustskyi Raion, Zakarpattia Oblast

Podobovets: 1,039 kWh per kWp a year, tilt 37° 10° east of south (PVGIS). 9.0% below the oblast median (1,141). #109 of 145 in the rayon, #542 of 613 in the oblast.

Khust, the rayon centre, is 56 km away. 672 m above sea level — above 500 m the DBN snow and wind are higher. 49 km away: Mukachevo, the nearest bigger centre, 1,165 — 10.8% less here. Snow and wind from the nearest regional centre in the DBN — Ужгород, 72 km. 10.95 m between rows, pitch 14.77 m (latitude 48.7°).

Yield of 1 kWp
1,039kWh/year
Tilt
37°10° east of south
10 kW
10,387kWh/year
Row pitch
14.77m · GCR 0.32
T_min
-38 °Cregion IIIA, Carpathian
Snow S₀ / wind W₀
1,340 / 370Pa

Ground frame designer

A ground frame for a solar plant: Podobovets

The designer opens with this place’s coordinates, latitude 48.7° for the row spacing and the DBN loads of the nearest regional centre — Ужгород, 72 km: snow 1,340 Pa, wind 370 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

42Jan61Feb93Mar106Apr114May118Jun126Jul126Aug101Sep76Oct45Nov29Dec

July: 126 kWh/kWp, December: 29 — 4.3 times less.

November: 45 against 53 in the oblast, 15.1% less.

Podobovets: plants, kWh
kWpA yearJulyDecember
55,194630145
1010,3871,260290
1515,5811,890435

Snow and wind: Ужгород

Example: a 10 kW ground frame

For the loads of Uzhhorod: 11.16 kWp, 18 panels, 366 kg of steel, 12 piles, materials ≈ 48,597 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Khustskyi RaionZakarpattia Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.