Solar plant: site data

Solar power plant in Krainie, Khustskyi Raion, Zakarpattia Oblast

Krainie: 1,139 kWh per kWp a year, tilt 37° 2° east of south (PVGIS). Exactly the oblast median (1,141). #48 of 145 in the rayon, #320 of 613 in the oblast.

Khust, the rayon centre, is 16 km away. 301 m above sea level. 16 km away: Khust, the nearest bigger centre, 978 — 16.4% more here. Snow and wind from the nearest regional centre in the DBN — Ужгород, 88 km. 10.67 m between rows, pitch 14.49 m (latitude 48.3°).

Yield of 1 kWp
1,139kWh/year
Tilt
37°2° east of south
10 kW
11,386kWh/year
Row pitch
14.49m · GCR 0.33
T_min
-38 °Cregion IIIA, Carpathian
Snow S₀ / wind W₀
1,340 / 370Pa

Ground frame designer

A ground frame for a solar plant: Krainie

The designer opens with this place’s coordinates, latitude 48.3° for the row spacing and the DBN loads of the nearest regional centre — Ужгород, 88 km: snow 1,340 Pa, wind 370 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

42Jan59Feb98Mar115Apr128May133Jun138Jul140Aug112Sep88Oct54Nov31Dec

August: 140 kWh/kWp, December: 31 — 4.5 times less.

January: 42 against 39 in the oblast, 7.7% more.

Krainie: plants, kWh
kWpA yearAugustDecember
55,693700155
1011,3861,400310
1517,0792,100465

Snow and wind: Ужгород

Example: a 10 kW ground frame

For the loads of Uzhhorod: 11.16 kWp, 18 panels, 366 kg of steel, 12 piles, materials ≈ 48,597 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Khustskyi RaionZakarpattia Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.