Solar plant: site data
Solar power plant in Bila Tserkva, Tiachivskyi Raion, Zakarpattia Oblast
Bila Tserkva: 1,151 kWh per kWp a year, tilt 38° 3° east of south (PVGIS). 0.8% above the oblast median (1,141). #11 of 66 in the rayon, #246 of 613 in the oblast.
Tyachiv, the rayon centre, is 25 km away. 294 m above sea level. 25 km away: Tyachiv, the nearest bigger centre, 1,158 — 0.6% less here. Snow and wind from the nearest regional centre in the DBN — Івано-Франківськ, 124 km. 10.66 m between rows, pitch 14.43 m (latitude 47.9°).
- Yield of 1 kWp
- 1,151kWh/year
- Tilt
- 38°3° east of south
- 10 kW
- 11,505kWh/year
- Row pitch
- 14.43m · GCR 0.33
- T_min
- -42 °Cregion II, south-eastern
- Snow S₀ / wind W₀
- 1,410 / 500Pa
Ground frame designer
A ground frame for a solar plant: Bila Tserkva
The designer opens with this place’s coordinates, latitude 47.9° for the row spacing and the DBN loads of the nearest regional centre — Івано-Франківськ, 124 km: snow 1,410 Pa, wind 500 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
July: 136 kWh/kWp, December: 36 — 3.8 times less.
December: 36 against 31 in the oblast, 16.1% more.
| kWp | A year | July | December |
|---|---|---|---|
| 5 | 5,753 | 680 | 180 |
| 10 | 11,505 | 1,360 | 360 |
| 15 | 17,258 | 2,040 | 540 |
Snow and wind: Івано-Франківськ
Example: a 10 kW ground frame
For the loads of Ivano-Frankivsk: 11.16 kWp, 18 panels, 410 kg of steel, 16 piles, materials ≈ 54,212 UAH.
How these numbers are computed
Nearby
- Solotvyno2 km1,151 kWh/kWp
- Serednie Vodiane4 km1,149 kWh/kWp
- Dobrik7 km1,151 kWh/kWp
- Nyzhnia Apsha8 km1,142 kWh/kWp
- Verkhnye Vodyane8 km1,133 kWh/kWp
- Velykyy Bychkiv9 km1,134 kWh/kWp
All places: Tiachivskyi RaionZakarpattia Oblast: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.