Solar plant: site data

Solar power plant in Perekorintsy, Mohyliv-Podilskyi Raion, Vinnytsia Oblast

Perekorintsy: 1,152 kWh per kWp a year, tilt 36° 2° east of south (PVGIS). 0.8% above the oblast median (1,143). #97 of 158 in the rayon, #324 of 1206 in the oblast.

Mohyliv-Podilskyy, the rayon centre, is 33 km away. 274 m above sea level. 33 km away: Mohyliv-Podilskyy, the nearest bigger centre, 1,160 — 0.7% less here. Snow and wind from the nearest regional centre in the DBN — Вінниця, 85 km. 10.73 m between rows, pitch 14.60 m (latitude 48.7°).

Yield of 1 kWp
1,152kWh/year
Tilt
36°2° east of south
10 kW
11,520kWh/year
Row pitch
14.60m · GCR 0.33
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,360 / 470Pa

Ground frame designer

A ground frame for a solar plant: Perekorintsy

The designer opens with this place’s coordinates, latitude 48.7° for the row spacing and the DBN loads of the nearest regional centre — Вінниця, 85 km: snow 1,360 Pa, wind 470 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

37Jan54Feb95Mar121Apr139May140Jun143Jul142Aug117Sep89Oct42Nov34Dec

July: 143 kWh/kWp, December: 34 — 4.2 times less.

December: 34 against 32 in the oblast, 6.3% more.

Perekorintsy: plants, kWh
kWpA yearJulyDecember
55,760715170
1011,5201,430340
1517,2802,145510

Snow and wind: Вінниця

Example: a 10 kW ground frame

For the loads of Vinnytsia: 11.16 kWp, 18 panels, 372 kg of steel, 12 piles, materials ≈ 49,705 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Mohyliv-Podilskyi RaionVinnytsia Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.