Solar plant: site data

Solar power plant in Turylche, Chortkivskyi Raion, Ternopil Oblast

Turylche: 1,116 kWh per kWp a year, tilt 36° 1° east of south (PVGIS). 2.1% above the oblast median (1,093). #157 of 296 in the rayon, #157 of 744 in the oblast.

Chortkiv, the rayon centre, is 40 km away. 234 m above sea level. 30 km away: Kamyanets-Podilskyi, the nearest bigger centre, 1,129 — 1.1% less here. Snow and wind from the nearest regional centre in the DBN — Чернівці, 57 km. 10.78 m between rows, pitch 14.65 m (latitude 48.8°).

Yield of 1 kWp
1,116kWh/year
Tilt
36°1° east of south
10 kW
11,156kWh/year
Row pitch
14.65m · GCR 0.33
T_min
-38 °Cregion IIIA, Carpathian
Snow S₀ / wind W₀
1,320 / 500Pa

Ground frame designer

A ground frame for a solar plant: Turylche

The designer opens with this place’s coordinates, latitude 48.8° for the row spacing and the DBN loads of the nearest regional centre — Чернівці, 57 km: snow 1,320 Pa, wind 500 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

37Jan51Feb94Mar118Apr133May134Jun141Jul137Aug113Sep86Oct40Nov32Dec

July: 141 kWh/kWp, December: 32 — 4.4 times less.

January: 37 against 34 in the oblast, 8.8% more.

Turylche: plants, kWh
kWpA yearJulyDecember
55,578705160
1011,1561,410320
1516,7342,115480

Snow and wind: Чернівці

Example: a 10 kW ground frame

For the loads of Chernivtsi: 11.16 kWp, 18 panels, 412 kg of steel, 16 piles, materials ≈ 54,638 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Chortkivskyi RaionTernopil Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.