Solar power plant in Kolomiitseve Ozero, Lubenskyi Raion, Poltava Oblast

Kolomiitseve Ozero: 1,141 kWh per kWp a year, tilt 37° 2° east of south (PVGIS). Exactly the oblast median (1,142). #75 of 346 in the rayon, #967 of 1856 in the oblast.

Lubny, the rayon centre, is 28 km away. 131 m above sea level. 28 km away: Lubny, the nearest bigger centre, the same 1,146. Snow and wind from the nearest regional centre in the DBN — Черкаси, 88 km. 11.89 m between rows, pitch 15.71 m (latitude 49.8°).

Yield of 1 kWp
1,141kWh/year
Tilt
37°2° east of south
10 kW
11,410kWh/year
Row pitch
15.71m · GCR 0.30
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,520 / 420Pa

Ground frame designer

A ground frame for a solar plant: Kolomiitseve Ozero

The designer opens with this place’s coordinates, latitude 49.8° for the row spacing and the DBN loads of the nearest regional centre — Черкаси, 88 km: snow 1,520 Pa, wind 420 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

33Jan55Feb92Mar120Apr140May144Jun148Jul146Aug116Sep84Oct38Nov25Dec

July: 148 kWh/kWp, December: 25 — 5.9 times less.

January: 33 against 35 in the oblast, 5.7% less.

Kolomiitseve Ozero: plants, kWh
kWpA yearJulyDecember
55,705740125
1011,4101,480250
1517,1152,220375

Snow and wind: Черкаси

Example: a 10 kW ground frame

For the loads of Cherkasy: 11.16 kWp, 18 panels, 372 kg of steel, 12 piles, materials ≈ 49,705 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Lubenskyi RaionPoltava Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.