Solar plant: site data

Solar power plant in Budzhak, Bolhradskyi Raion, Odesa Oblast

Budzhak: 1,244 kWh per kWp a year, tilt 36° 4° east of south (PVGIS). 1.9% above the oblast median (1,221). #63 of 99 in the rayon, #376 of 1177 in the oblast.

Bolhrad, the rayon centre, is 84 km away. 56 m above sea level. 84 km away: Bolhrad, the nearest bigger centre, 1,283 — 3.0% less here. Snow and wind from the nearest regional centre in the DBN — Одеса, 116 km. 9.14 m between rows, pitch 13.01 m (latitude 46.3°).

Yield of 1 kWp
1,244kWh/year
Tilt
36°4° east of south
10 kW
12,444kWh/year
Row pitch
13.01m · GCR 0.37
T_min
-42 °Cregion II, south-eastern
Snow S₀ / wind W₀
880 / 460Pa

Ground frame designer

A ground frame for a solar plant: Budzhak

The designer opens with this place’s coordinates, latitude 46.3° for the row spacing and the DBN loads of the nearest regional centre — Одеса, 116 km: snow 880 Pa, wind 460 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

43Jan61Feb107Mar125Apr142May141Jun149Jul148Aug126Sep101Oct56Nov45Dec

July: 149 kWh/kWp, January: 43 — 3.5 times less.

December: 45 against 38 in the oblast, 18.4% more.

Budzhak: plants, kWh
kWpA yearJulyJanuary
56,222745215
1012,4441,490430
1518,6662,235645

Snow and wind: Одеса

Example: a 10 kW ground frame

For the loads of Odesa: 11.16 kWp, 18 panels, 349 kg of steel, 12 piles, materials ≈ 47,980 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed